Levanto By Oro24 construction photos

109 photos taken by Dubai Land Department engineers at 13 site inspections, newest first. The percentage is how much of Levanto By Oro24 was built on the day of each visit.

9 September 202666% built

10 July 202660% built

23 April 202656% built

29 January 202646% built

19 September 202529% built

27 May 202525% built

27 December 202416% built

30 September 20247.6% built

20 March 20242.9% built

26 September 20232.0% built

13 June 20230.7% built

16 February 20230% built

21 November 20220% built

Back to Levanto By Oro24 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.