Hamilton House construction progress

The register lists Hamilton House in Jumeirah Village Circle as complete, with a registered completion date of January 2025. Its last site inspection on record was in February 2025. The developer is Ellington Properties Development.

100%

Built, at the site inspection of 5 February 2025

Construction complete

Registered completion date
January 2025
Construction started
December 2022
First registered
January 2023
Units
102
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
هاملتون هاوس
Project number
2538
Site inspections
7

Schedule

The register lists Hamilton House as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202320242025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

5 February 2025

100%+4.1 pts

  • Hamilton House construction site, inspection photo 1, 5 February 2025
  • Hamilton House construction site, inspection photo 2, 5 February 2025
  • Hamilton House construction site, inspection photo 3, 5 February 2025
  • Hamilton House construction site, inspection photo 4, 5 February 2025

27 November 2024

96%+28 pts

  • Hamilton House construction site, inspection photo 1, 27 November 2024
  • Hamilton House construction site, inspection photo 2, 27 November 2024
  • Hamilton House construction site, inspection photo 3, 27 November 2024
  • Hamilton House construction site, inspection photo 4, 27 November 2024

5 July 2024

68%+25 pts

  • Hamilton House construction site, inspection photo 1, 5 July 2024
  • Hamilton House construction site, inspection photo 2, 5 July 2024
  • Hamilton House construction site, inspection photo 3, 5 July 2024
  • Hamilton House construction site, inspection photo 4, 5 July 2024

20 March 2024

42%+18 pts

  • Hamilton House construction site, inspection photo 1, 20 March 2024
  • Hamilton House construction site, inspection photo 2, 20 March 2024
  • Hamilton House construction site, inspection photo 3, 20 March 2024
  • Hamilton House construction site, inspection photo 4, 20 March 2024

30 October 2023

25%+24 pts

  • Hamilton House construction site, inspection photo 1, 30 October 2023
  • Hamilton House construction site, inspection photo 2, 30 October 2023
  • Hamilton House construction site, inspection photo 3, 30 October 2023
  • Hamilton House construction site, inspection photo 4, 30 October 2023

11 May 2023

0.8%+0.7 pts

  • Hamilton House construction site, inspection photo 1, 11 May 2023
  • Hamilton House construction site, inspection photo 2, 11 May 2023
  • Hamilton House construction site, inspection photo 3, 11 May 2023
  • Hamilton House construction site, inspection photo 4, 11 May 2023

22 December 2022

0.1%

  • Hamilton House construction site, inspection photo 1, 22 December 2022
  • Hamilton House construction site, inspection photo 2, 22 December 2022
  • Hamilton House construction site, inspection photo 3, 22 December 2022

All 43 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Ellington Properties Development has 18 projects under construction in Dubai; 6 have passed their registered completion date.

Own a unit in Hamilton House?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Hamilton House handover date?
Construction of Hamilton House is recorded as complete, with a registered completion date of January 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Hamilton House?
Hamilton House was 100% built at the site inspection on 5 February 2025. The site has been inspected 7 times since December 2022. The Land Department took 43 site photos at its inspections.
Is Hamilton House delayed?
The register lists construction as complete.
Who is building Hamilton House?
The registered developer is Ellington Properties Development. It has 18 other projects under construction in Dubai.
Which bank holds the escrow account for Hamilton House?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.