Elitz 3 By Danube construction progress
No completion date is registered for Elitz 3 By Danube in Jumeirah Village Circle yet. At the last site inspection, in September 2026, it was 38% built. The developer is Danube Properties Development.
38%
Built, at the site inspection of 18 September 2026
- Finish at recent pace
- August 2029
- Construction started
- December 2023
- First registered
- October 2023
- Developer
- Danube Properties Development
- Community
- Jumeirah Village Circle
- Units
- 692
- Escrow bank
- Commercial Bank of Dubai
- Name in Arabic
- إليتز 3 من دانوب
- Project number
- 2722
- Site inspections
- 10
Schedule
Since October 2025 Elitz 3 By Danube has added about 1.8 points a month. At that rate the site reaches 100% around August 2029. No completion date is on record to compare it with.
Site inspections
18 September 2026
38%+5.5 pts
12 May 2026
32%+6.6 pts
4 February 2026
26%+5.9 pts
19 November 2025
20%+1.0 pts
28 October 2025
19%+1.7 pts
16 September 2025
17%+5.1 pts
2 June 2025
12%+8.3 pts
23 April 2024
4.0%+3.9 pts
28 December 2023
0%+0.0 pts
12 September 2023
0%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Danube Properties Development has 23 projects under construction in Dubai; 4 have passed their registered completion date.
Own a unit in Elitz 3 By Danube?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Elitz 3 By Danube handover date?
- No completion date is on record for Elitz 3 By Danube yet. Handover follows completion, so there is no date to give.
- What is the latest construction update on Elitz 3 By Danube?
- Elitz 3 By Danube was 38% built at the site inspection on 18 September 2026. The site has been inspected 10 times since September 2023. The Land Department took 70 site photos at its inspections.
- Who is building Elitz 3 By Danube?
- The registered developer is Danube Properties Development. It has 22 other projects under construction in Dubai.
- Which bank holds the escrow account for Elitz 3 By Danube?
- Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Elitz By DanubeAlso by Danube Properties Development. 92%, Due December 2025, passed.
- Viewz 1 By DanubeAlso by Danube Properties Development. 66%, Due June 2026, passed.
- Viewz 2 By DanubeAlso by Danube Properties Development. 65%, Due June 2026, passed.
- Fashionz 1 By DanubeAlso by Danube Properties Development. 40%.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.






.jpeg&w=3840&q=75)














.jpg&w=3840&q=75)






.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)