Elitz 3 By Danube construction progress

Elitz 3 By Danube in Jumeirah Village Circle is 38% built at the Land Department inspection of September 2026. Developer Danube Properties Development.

38%

Built, at the Land Department site inspection of 18 September 2026

Finish at recent pace
August 2029
Construction started
December 2023
Registered with the Land Department
October 2023
Units
692
Escrow bank
Commercial Bank of Dubai
Name in Arabic
إليتز 3 من دانوب
Land Department project number
2722
Land Department site inspections
10

Schedule

Since October 2025 Elitz 3 By Danube has added about 1.8 points a month. At that rate the site reaches 100% around August 2029. The Land Department has no completion date on record to compare it with.

0%25%50%75%100%202420252026
Progress at each Land Department site inspection

Site inspections

18 September 2026

38%+5.5 pts

  • Elitz 3 By Danube construction site, Land Department inspection photo 1, 18 September 2026
  • Elitz 3 By Danube construction site, Land Department inspection photo 2, 18 September 2026
  • Elitz 3 By Danube construction site, Land Department inspection photo 3, 18 September 2026
  • Elitz 3 By Danube construction site, Land Department inspection photo 4, 18 September 2026

12 May 2026

32%+6.6 pts

  • Elitz 3 By Danube construction site, Land Department inspection photo 1, 12 May 2026
  • Elitz 3 By Danube construction site, Land Department inspection photo 2, 12 May 2026
  • Elitz 3 By Danube construction site, Land Department inspection photo 3, 12 May 2026
  • Elitz 3 By Danube construction site, Land Department inspection photo 4, 12 May 2026

4 February 2026

26%+5.9 pts

  • Elitz 3 By Danube construction site, Land Department inspection photo 1, 4 February 2026
  • Elitz 3 By Danube construction site, Land Department inspection photo 2, 4 February 2026
  • Elitz 3 By Danube construction site, Land Department inspection photo 3, 4 February 2026
  • Elitz 3 By Danube construction site, Land Department inspection photo 4, 4 February 2026

19 November 2025

20%+1.0 pts

  • Elitz 3 By Danube construction site, Land Department inspection photo 1, 19 November 2025
  • Elitz 3 By Danube construction site, Land Department inspection photo 2, 19 November 2025
  • Elitz 3 By Danube construction site, Land Department inspection photo 3, 19 November 2025
  • Elitz 3 By Danube construction site, Land Department inspection photo 4, 19 November 2025

28 October 2025

19%+1.7 pts

  • Elitz 3 By Danube construction site, Land Department inspection photo 1, 28 October 2025
  • Elitz 3 By Danube construction site, Land Department inspection photo 2, 28 October 2025
  • Elitz 3 By Danube construction site, Land Department inspection photo 3, 28 October 2025
  • Elitz 3 By Danube construction site, Land Department inspection photo 4, 28 October 2025

16 September 2025

17%+5.1 pts

  • Elitz 3 By Danube construction site, Land Department inspection photo 1, 16 September 2025
  • Elitz 3 By Danube construction site, Land Department inspection photo 2, 16 September 2025
  • Elitz 3 By Danube construction site, Land Department inspection photo 3, 16 September 2025
  • Elitz 3 By Danube construction site, Land Department inspection photo 4, 16 September 2025

2 June 2025

12%+8.3 pts

  • Elitz 3 By Danube construction site, Land Department inspection photo 1, 2 June 2025
  • Elitz 3 By Danube construction site, Land Department inspection photo 2, 2 June 2025
  • Elitz 3 By Danube construction site, Land Department inspection photo 3, 2 June 2025
  • Elitz 3 By Danube construction site, Land Department inspection photo 4, 2 June 2025

23 April 2024

4.0%+3.9 pts

  • Elitz 3 By Danube construction site, Land Department inspection photo 1, 23 April 2024
  • Elitz 3 By Danube construction site, Land Department inspection photo 2, 23 April 2024
  • Elitz 3 By Danube construction site, Land Department inspection photo 3, 23 April 2024
  • Elitz 3 By Danube construction site, Land Department inspection photo 4, 23 April 2024

28 December 2023

0%+0.0 pts

  • Elitz 3 By Danube construction site, Land Department inspection photo 1, 28 December 2023
  • Elitz 3 By Danube construction site, Land Department inspection photo 2, 28 December 2023
  • Elitz 3 By Danube construction site, Land Department inspection photo 3, 28 December 2023
  • Elitz 3 By Danube construction site, Land Department inspection photo 4, 28 December 2023

12 September 2023

0%

  • Elitz 3 By Danube construction site, Land Department inspection photo 1, 12 September 2023
  • Elitz 3 By Danube construction site, Land Department inspection photo 2, 12 September 2023
  • Elitz 3 By Danube construction site, Land Department inspection photo 3, 12 September 2023
  • Elitz 3 By Danube construction site, Land Department inspection photo 4, 12 September 2023

All 70 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average.

Danube Properties Development has 23 projects under construction in Dubai; 4 have passed their registered completion date.

Own a unit in Elitz 3 By Danube?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Elitz 3 By Danube be completed?
The Land Department has no completion date on record for Elitz 3 By Danube yet.
How much of Elitz 3 By Danube is built?
38%, measured at the Land Department site inspection on 18 September 2026. The Land Department engineers have inspected the site 10 times since September 2023.
Who is building Elitz 3 By Danube?
The registered developer is Danube Properties Development. It has 22 other projects under construction in Dubai.
Which bank holds the escrow account for Elitz 3 By Danube?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.