Elitz 3 By Danube construction photos
70 photos taken by Dubai Land Department engineers at 10 site inspections, newest first. The percentage is how much of Elitz 3 By Danube was built on the day of each visit.
18 September 202638% built
12 May 202632% built
4 February 202626% built
19 November 202520% built
28 October 202519% built
16 September 202517% built
2 June 202512% built
23 April 20244.0% built
28 December 20230% built
12 September 20230% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.