Elitz 3 By Danube construction photos

70 photos from 10 site inspections, newest first. The percentage is how much of Elitz 3 By Danube was built on the day of each visit.

18 September 202638% built

12 May 202632% built

4 February 202626% built

19 November 202520% built

28 October 202519% built

16 September 202517% built

2 June 202512% built

23 April 20244.0% built

28 December 20230% built

12 September 20230% built

Back to Elitz 3 By Danube construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.