Elitz 2 By Danube construction progress
No completion date is registered for Elitz 2 By Danube in Jumeirah Village Circle yet. At the last site inspection, in September 2026, it was 20% built. The developer is Danube Properties Development.
20%
Built, at the site inspection of 28 September 2026
- Finish at recent pace
- January 2033
- Construction started
- November 2023
- First registered
- August 2023
- Developer
- Danube Properties Development
- Community
- Jumeirah Village Circle
- Units
- 801
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- إليتز 2 من دانوب
- Project number
- 2693
- Site inspections
- 9
Schedule
Since December 2025 Elitz 2 By Danube has added about 1.1 points a month. At that rate the site reaches 100% around January 2033. No completion date is on record to compare it with.
Site inspections
28 September 2026
20%+3.2 pts
30 June 2026
17%+3.0 pts
23 March 2026
14%+3.5 pts
24 December 2025
10%+1.6 pts
28 January 2025
8.7%+2.9 pts
11 December 2024
5.8%+5.4 pts
12 April 2024
0.4%+0.4 pts
26 October 2023
0%+0.0 pts
19 July 2023
0%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Danube Properties Development has 23 projects under construction in Dubai; 4 have passed their registered completion date.
Own a unit in Elitz 2 By Danube?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Elitz 2 By Danube handover date?
- No completion date is on record for Elitz 2 By Danube yet. Handover follows completion, so there is no date to give.
- What is the latest construction update on Elitz 2 By Danube?
- Elitz 2 By Danube was 20% built at the site inspection on 28 September 2026. The site has been inspected 9 times since July 2023. The Land Department took 43 site photos at its inspections.
- Who is building Elitz 2 By Danube?
- The registered developer is Danube Properties Development. It has 22 other projects under construction in Dubai.
- Which bank holds the escrow account for Elitz 2 By Danube?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Elitz By DanubeAlso by Danube Properties Development. 92%, Due December 2025, passed.
- Viewz 1 By DanubeAlso by Danube Properties Development. 66%, Due June 2026, passed.
- Viewz 2 By DanubeAlso by Danube Properties Development. 65%, Due June 2026, passed.
- Fashionz 1 By DanubeAlso by Danube Properties Development. 40%.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)





.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)