Elitz 2 By Danube construction photos
43 photos from 9 site inspections, newest first. The percentage is how much of Elitz 2 By Danube was built on the day of each visit.
28 September 202620% built
30 June 202617% built
23 March 202614% built
24 December 202510% built
28 January 20258.7% built
11 December 20245.8% built
12 April 20240.4% built
26 October 20230% built
19 July 20230% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.