Belgravia Square construction progress

The register lists Belgravia Square in Jumeirah Village Circle as complete, with a registered completion date of November 2023. Its last site inspection on record was in November 2023. The developer is Ellington Properties Development.

100%

Built, at the site inspection of 8 November 2023

Construction complete

Registered completion date
November 2023
Construction started
May 2018
First registered
November 2018
Units
225
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
بلغرافيا سكوير
Project number
2100
Site inspections
12

Schedule

The register lists Belgravia Square as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20192020202120222023
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

8 November 2023

100%+12 pts

  • Belgravia Square construction site, inspection photo 1, 8 November 2023
  • Belgravia Square construction site, inspection photo 2, 8 November 2023
  • Belgravia Square construction site, inspection photo 3, 8 November 2023
  • Belgravia Square construction site, inspection photo 4, 8 November 2023

15 May 2023

88%+7.7 pts

  • Belgravia Square construction site, inspection photo 1, 15 May 2023
  • Belgravia Square construction site, inspection photo 2, 15 May 2023
  • Belgravia Square construction site, inspection photo 3, 15 May 2023
  • Belgravia Square construction site, inspection photo 4, 15 May 2023

2 January 2023

80%+18 pts

  • Belgravia Square construction site, inspection photo 1, 2 January 2023
  • Belgravia Square construction site, inspection photo 2, 2 January 2023
  • Belgravia Square construction site, inspection photo 3, 2 January 2023
  • Belgravia Square construction site, inspection photo 4, 2 January 2023

23 September 2022

63%+12 pts

  • Belgravia Square construction site, inspection photo 1, 23 September 2022
  • Belgravia Square construction site, inspection photo 2, 23 September 2022
  • Belgravia Square construction site, inspection photo 3, 23 September 2022
  • Belgravia Square construction site, inspection photo 4, 23 September 2022

25 March 2022

51%+8.5 pts

  • Belgravia Square construction site, inspection photo 1, 25 March 2022
  • Belgravia Square construction site, inspection photo 2, 25 March 2022
  • Belgravia Square construction site, inspection photo 3, 25 March 2022
  • Belgravia Square construction site, inspection photo 4, 25 March 2022

11 November 2021

42%+6.7 pts

  • Belgravia Square construction site, inspection photo 1, 11 November 2021
  • Belgravia Square construction site, inspection photo 2, 11 November 2021
  • Belgravia Square construction site, inspection photo 3, 11 November 2021
  • Belgravia Square construction site, inspection photo 4, 11 November 2021

16 September 2021

36%+7.6 pts

  • Belgravia Square construction site, inspection photo 1, 16 September 2021
  • Belgravia Square construction site, inspection photo 2, 16 September 2021
  • Belgravia Square construction site, inspection photo 3, 16 September 2021
  • Belgravia Square construction site, inspection photo 4, 16 September 2021

29 April 2021

28%+7.3 pts

  • Belgravia Square construction site, inspection photo 1, 29 April 2021
  • Belgravia Square construction site, inspection photo 2, 29 April 2021
  • Belgravia Square construction site, inspection photo 3, 29 April 2021
  • Belgravia Square construction site, inspection photo 4, 29 April 2021

10 June 2020

21%+0.6 pts

  • Belgravia Square construction site, inspection photo 1, 10 June 2020
  • Belgravia Square construction site, inspection photo 2, 10 June 2020
  • Belgravia Square construction site, inspection photo 3, 10 June 2020
  • Belgravia Square construction site, inspection photo 4, 10 June 2020

7 November 2019

20%+16 pts

  • Belgravia Square construction site, inspection photo 1, 7 November 2019
  • Belgravia Square construction site, inspection photo 2, 7 November 2019
  • Belgravia Square construction site, inspection photo 3, 7 November 2019
  • Belgravia Square construction site, inspection photo 4, 7 November 2019

All 115 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Ellington Properties Development has 18 projects under construction in Dubai; 6 have passed their registered completion date.

Own a unit in Belgravia Square?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Belgravia Square handover date?
Construction of Belgravia Square is recorded as complete, with a registered completion date of November 2023. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Belgravia Square?
Belgravia Square was 100% built at the site inspection on 8 November 2023. The site has been inspected 12 times since November 2018. The Land Department took 115 site photos at its inspections.
Is Belgravia Square delayed?
The register lists construction as complete.
Who is building Belgravia Square?
The registered developer is Ellington Properties Development. It has 18 other projects under construction in Dubai.
Which bank holds the escrow account for Belgravia Square?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.