Belgravia 2 construction progress
The register lists Belgravia 2 in Jumeirah Village Circle as complete, with a registered completion date of February 2019. Its last site inspection on record was in February 2019. The developer is Ellington Properties Development.
100%
Built, at the site inspection of 6 February 2019
Construction complete
- Registered completion date
- February 2019
- Construction started
- July 2016
- First registered
- December 2016
- Developer
- Ellington Properties Development
- Community
- Jumeirah Village Circle
- Units
- 188
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- بلغرافيا 2
- Project number
- 1820
- Site inspections
- 6
Schedule
The register lists Belgravia 2 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
6 February 2019
100%+9.8 pts
2 August 2018
90%+20 pts
12 March 2018
70%+19 pts
28 November 2017
51%+20 pts
1 August 2017
31%+11 pts
11 April 2017
20%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Ellington Properties Development has 18 projects under construction in Dubai; 6 have passed their registered completion date.
Own a unit in Belgravia 2?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the Belgravia 2 handover date?
- Construction of Belgravia 2 is recorded as complete, with a registered completion date of February 2019. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on Belgravia 2?
- Belgravia 2 was 100% built at the site inspection on 6 February 2019. The site has been inspected 6 times since April 2017. The Land Department took 52 site photos at its inspections.
- Is Belgravia 2 delayed?
- The register lists construction as complete.
- Who is building Belgravia 2?
- The registered developer is Ellington Properties Development. It has 18 other projects under construction in Dubai.
- Which bank holds the escrow account for Belgravia 2?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The PortmanAlso by Ellington Properties Development. 79%, Due September 2025, passed.
- The HighburyAlso by Ellington Properties Development. 80%.
- Uh West By EllingtonAlso by Ellington Properties Development. 84%, Due March 2026, passed.
- Uh East By EllingtonAlso by Ellington Properties Development. 63%, Due March 2026, passed.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpg&w=3840&q=75)

.jpg&w=3840&q=75)





