Belgravia 2 construction progress

The register lists Belgravia 2 in Jumeirah Village Circle as complete, with a registered completion date of February 2019. Its last site inspection on record was in February 2019. The developer is Ellington Properties Development.

100%

Built, at the site inspection of 6 February 2019

Construction complete

Registered completion date
February 2019
Construction started
July 2016
First registered
December 2016
Units
188
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
بلغرافيا 2
Project number
1820
Site inspections
6

Schedule

The register lists Belgravia 2 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201720182019
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

6 February 2019

100%+9.8 pts

  • Belgravia 2 construction site, inspection photo 1, 6 February 2019
  • Belgravia 2 construction site, inspection photo 2, 6 February 2019
  • Belgravia 2 construction site, inspection photo 3, 6 February 2019
  • Belgravia 2 construction site, inspection photo 4, 6 February 2019

2 August 2018

90%+20 pts

  • Belgravia 2 construction site, inspection photo 1, 2 August 2018
  • Belgravia 2 construction site, inspection photo 2, 2 August 2018
  • Belgravia 2 construction site, inspection photo 3, 2 August 2018
  • Belgravia 2 construction site, inspection photo 4, 2 August 2018

12 March 2018

70%+19 pts

  • Belgravia 2 construction site, inspection photo 1, 12 March 2018
  • Belgravia 2 construction site, inspection photo 2, 12 March 2018
  • Belgravia 2 construction site, inspection photo 3, 12 March 2018
  • Belgravia 2 construction site, inspection photo 4, 12 March 2018

28 November 2017

51%+20 pts

  • Belgravia 2 construction site, inspection photo 1, 28 November 2017
  • Belgravia 2 construction site, inspection photo 2, 28 November 2017
  • Belgravia 2 construction site, inspection photo 3, 28 November 2017
  • Belgravia 2 construction site, inspection photo 4, 28 November 2017

1 August 2017

31%+11 pts

  • Belgravia 2 construction site, inspection photo 1, 1 August 2017
  • Belgravia 2 construction site, inspection photo 2, 1 August 2017
  • Belgravia 2 construction site, inspection photo 3, 1 August 2017
  • Belgravia 2 construction site, inspection photo 4, 1 August 2017

11 April 2017

20%

  • Belgravia 2 construction site, inspection photo 1, 11 April 2017
  • Belgravia 2 construction site, inspection photo 2, 11 April 2017

All 52 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Ellington Properties Development has 18 projects under construction in Dubai; 6 have passed their registered completion date.

Own a unit in Belgravia 2?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Belgravia 2 handover date?
Construction of Belgravia 2 is recorded as complete, with a registered completion date of February 2019. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Belgravia 2?
Belgravia 2 was 100% built at the site inspection on 6 February 2019. The site has been inspected 6 times since April 2017. The Land Department took 52 site photos at its inspections.
Is Belgravia 2 delayed?
The register lists construction as complete.
Who is building Belgravia 2?
The registered developer is Ellington Properties Development. It has 18 other projects under construction in Dubai.
Which bank holds the escrow account for Belgravia 2?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.