Nautis Residences construction progress
The registered completion date for Nautis Residences in Palm Deira is August 2027. At the last site inspection, in April 2026, it was 0.9% built. The developer is Stamn Real Estate Development.
0.9%
Built, at the site inspection of 28 April 2026
Running behind its date
- Registered completion date
- August 2027
- Finish at recent pace
- February 2146
- Construction started
- August 2025
- First registered
- May 2025
- Developer
- Stamn Real Estate Development
- Community
- Palm Deira
- Units
- 63
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- ناتس ريزيدانسيز
- Project number
- 3654
- Site inspections
- 2
Schedule
Between April 2025 and April 2026 the site added about 0.1 points a month. At that rate it would finish around February 2146, more than three months after its registered date of August 2027.
Site inspections
28 April 2026
0.9%+0.9 pts
9 April 2025
0%
Context
Palm Deira has 94 projects under construction, 24% built on average.
Stamn Real Estate Development has 3 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Nautis Residences?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Nautis Residences handover date?
- The registered completion date is August 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2146. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Nautis Residences?
- Nautis Residences was 0.9% built at the site inspection on 28 April 2026. The site has been inspected 2 times since April 2025. The Land Department took 6 site photos at its inspections.
- Is Nautis Residences delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2027.
- Who is building Nautis Residences?
- The registered developer is Stamn Real Estate Development. It has 2 other projects under construction in Dubai.
- Which bank holds the escrow account for Nautis Residences?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Stamn OneAlso by Stamn Real Estate Development. 42%, Due October 2026, passed.
- Stamn YuniAlso by Stamn Real Estate Development. 21%, Due March 2027.
- Bay Residences Dubai IslandsNearby in Palm Deira. 48%, Due October 2026, passed.
- Beach Residences Dubai IslandsNearby in Palm Deira. 29%.
- Bay Villas - Dubai IslandsNearby in Palm Deira. 23%, Due May 2027.
- Edgewater ResidencesNearby in Palm Deira. 48%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.





