Nautis Residences construction progress

Nautis Residences in Palm Deira is 0.9% built at the Land Department inspection of April 2026. Developer Stamn Real Estate Development. Completion registered for August 2027.

0.9%

Built, at the Land Department site inspection of 28 April 2026

Running behind its date

Completion date (Land Department)
August 2027
Finish at recent pace
February 2146
Construction started
August 2025
Registered with the Land Department
May 2025
Community
Palm Deira
Units
63
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
ناتس ريزيدانسيز
Land Department project number
3654
Land Department site inspections
2

Schedule

Between April 2025 and April 2026 the site added about 0.1 points a month. At that rate it would finish around February 2146, more than three months after the August 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

28 April 2026

0.9%+0.9 pts

  • Nautis Residences construction site, Land Department inspection photo 1, 28 April 2026
  • Nautis Residences construction site, Land Department inspection photo 2, 28 April 2026
  • Nautis Residences construction site, Land Department inspection photo 3, 28 April 2026
  • Nautis Residences construction site, Land Department inspection photo 4, 28 April 2026

9 April 2025

0%

  • Nautis Residences construction site, Land Department inspection photo 1, 9 April 2025
  • Nautis Residences construction site, Land Department inspection photo 2, 9 April 2025

All 6 site photos, by inspection date

Context

Palm Deira has 95 projects under construction, 22% built on average. Nautis Residences is behind that average.

Stamn Real Estate Development has 3 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Nautis Residences?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Nautis Residences be completed?
The completion date registered with the Dubai Land Department is August 2027. At the pace of its recent inspections the site would reach 100% around February 2146. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Nautis Residences is built?
0.9%, measured at the Land Department site inspection on 28 April 2026. The Land Department engineers have inspected the site 2 times since April 2025.
Is Nautis Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2027.
Who is building Nautis Residences?
The registered developer is Stamn Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Nautis Residences?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.