Nautis Residences construction progress
Nautis Residences in Palm Deira is 0.9% built at the Land Department inspection of April 2026. Developer Stamn Real Estate Development. Completion registered for August 2027.
0.9%
Built, at the Land Department site inspection of 28 April 2026
Running behind its date
- Completion date (Land Department)
- August 2027
- Finish at recent pace
- February 2146
- Construction started
- August 2025
- Registered with the Land Department
- May 2025
- Developer
- Stamn Real Estate Development
- Community
- Palm Deira
- Units
- 63
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- ناتس ريزيدانسيز
- Land Department project number
- 3654
- Land Department site inspections
- 2
Schedule
Between April 2025 and April 2026 the site added about 0.1 points a month. At that rate it would finish around February 2146, more than three months after the August 2027 date registered with the Land Department.
Site inspections
28 April 2026
0.9%+0.9 pts
9 April 2025
0%
Context
Palm Deira has 95 projects under construction, 22% built on average. Nautis Residences is behind that average.
Stamn Real Estate Development has 3 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Nautis Residences?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Nautis Residences be completed?
- The completion date registered with the Dubai Land Department is August 2027. At the pace of its recent inspections the site would reach 100% around February 2146. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Nautis Residences is built?
- 0.9%, measured at the Land Department site inspection on 28 April 2026. The Land Department engineers have inspected the site 2 times since April 2025.
- Is Nautis Residences delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2027.
- Who is building Nautis Residences?
- The registered developer is Stamn Real Estate Development. It has 2 other projects under construction in Dubai.
- Which bank holds the escrow account for Nautis Residences?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Stamn OneAlso by Stamn Real Estate Development. 42%, Due October 2026.
- Stamn YuniAlso by Stamn Real Estate Development. 12%, Due March 2027.
- Bay Residences Dubai IslandsNearby in Palm Deira. 48%, Due October 2026.
- Beach Residences Dubai IslandsNearby in Palm Deira. 29%.
- Bay Villas - Dubai IslandsNearby in Palm Deira. 23%, Due May 2027.
- Edgewater ResidencesNearby in Palm Deira. 48%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.