Enso Jade construction photos
33 photos taken by Dubai Land Department engineers at 6 site inspections, newest first. The percentage is how much of Enso Jade was built on the day of each visit.
14 July 202642% built
13 April 202634% built
8 January 202621% built
20 October 202514% built
9 June 20258.1% built
12 September 20240% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.