171 Garden Heights construction photos
34 photos from 6 site inspections, newest first. The percentage is how much of 171 Garden Heights was built on the day of each visit.
8 June 202634% built
24 February 202626% built
12 November 202514% built
16 July 20256.7% built
2 April 20254.0% built
19 June 20240% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.