Al Helal Al Zahaby 3 construction progress

The register lists Al Helal Al Zahaby 3 in International City Phase 3 as complete, with a registered completion date of August 2023. Its last site inspection on record was in November 2023. The developer is Al Helal Al Zahaby Real Estate Development.

100%

Built, at the site inspection of 8 November 2023

Construction complete

Registered completion date
August 2023
Construction started
March 2022
First registered
February 2023
Units
67
Escrow bank
Emirates Islamic Bank
Name in Arabic
الهلال الذهبي 3
Project number
2468
Site inspections
2

Schedule

The register lists Al Helal Al Zahaby 3 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2023
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

8 November 2023

100%+50 pts

  • Al Helal Al Zahaby 3 construction site, inspection photo 1, 8 November 2023
  • Al Helal Al Zahaby 3 construction site, inspection photo 2, 8 November 2023
  • Al Helal Al Zahaby 3 construction site, inspection photo 3, 8 November 2023
  • Al Helal Al Zahaby 3 construction site, inspection photo 4, 8 November 2023

30 December 2022

50%

  • Al Helal Al Zahaby 3 construction site, inspection photo 1, 30 December 2022
  • Al Helal Al Zahaby 3 construction site, inspection photo 2, 30 December 2022
  • Al Helal Al Zahaby 3 construction site, inspection photo 3, 30 December 2022
  • Al Helal Al Zahaby 3 construction site, inspection photo 4, 30 December 2022

All 25 site photos, by inspection date

Context

International City Phase 3 has 20 projects under construction, 28% built on average.

Al Helal Al Zahaby Real Estate Development has 4 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Al Helal Al Zahaby 3?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Al Helal Al Zahaby 3 handover date?
Construction of Al Helal Al Zahaby 3 is recorded as complete, with a registered completion date of August 2023. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Al Helal Al Zahaby 3?
Al Helal Al Zahaby 3 was 100% built at the site inspection on 8 November 2023. The site has been inspected 2 times since December 2022. The Land Department took 25 site photos at its inspections.
Is Al Helal Al Zahaby 3 delayed?
The register lists construction as complete.
Who is building Al Helal Al Zahaby 3?
The registered developer is Al Helal Al Zahaby Real Estate Development. It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for Al Helal Al Zahaby 3?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.