Glitz Residence 2 construction progress

The register lists Glitz Residence 2 in Dubai Studio City as complete, with a registered completion date of July 2017. Its last site inspection on record was in December 2017. The developer is Danube Properties Development.

100%

Built, at the site inspection of 5 December 2017

Construction complete

Registered completion date
July 2017
Construction started
January 2015
First registered
December 2014
Units
151
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
جليتس ريزيدنس 2
Project number
1615
Site inspections
6

Schedule

The register lists Glitz Residence 2 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20162017
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

5 December 2017

100%+18 pts

  • Glitz Residence 2 construction site, inspection photo 1, 5 December 2017
  • Glitz Residence 2 construction site, inspection photo 2, 5 December 2017
  • Glitz Residence 2 construction site, inspection photo 3, 5 December 2017
  • Glitz Residence 2 construction site, inspection photo 4, 5 December 2017

28 March 2017

82%+11 pts

  • Glitz Residence 2 construction site, inspection photo 1, 28 March 2017
  • Glitz Residence 2 construction site, inspection photo 2, 28 March 2017
  • Glitz Residence 2 construction site, inspection photo 3, 28 March 2017
  • Glitz Residence 2 construction site, inspection photo 4, 28 March 2017

11 January 2017

71%+17 pts

  • Glitz Residence 2 construction site, inspection photo 1, 11 January 2017
  • Glitz Residence 2 construction site, inspection photo 2, 11 January 2017
  • Glitz Residence 2 construction site, inspection photo 3, 11 January 2017
  • Glitz Residence 2 construction site, inspection photo 4, 11 January 2017

22 August 2016

54%+28 pts

  • Glitz Residence 2 construction site, inspection photo 1, 22 August 2016
  • Glitz Residence 2 construction site, inspection photo 2, 22 August 2016
  • Glitz Residence 2 construction site, inspection photo 3, 22 August 2016
  • Glitz Residence 2 construction site, inspection photo 4, 22 August 2016

4 April 2016

26%+21 pts

  • Glitz Residence 2 construction site, inspection photo 1, 4 April 2016
  • Glitz Residence 2 construction site, inspection photo 2, 4 April 2016
  • Glitz Residence 2 construction site, inspection photo 3, 4 April 2016

7 September 2015

5.1%

  • Glitz Residence 2 construction site, inspection photo 1, 7 September 2015
  • Glitz Residence 2 construction site, inspection photo 2, 7 September 2015
  • Glitz Residence 2 construction site, inspection photo 3, 7 September 2015

All 38 site photos, by inspection date

Context

Dubai Studio City has 8 projects under construction, 53% built on average.

Danube Properties Development has 23 projects under construction in Dubai; 4 have passed their registered completion date.

Own a unit in Glitz Residence 2?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Glitz Residence 2 handover date?
Construction of Glitz Residence 2 is recorded as complete, with a registered completion date of July 2017. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Glitz Residence 2?
Glitz Residence 2 was 100% built at the site inspection on 5 December 2017. The site has been inspected 6 times since September 2015. The Land Department took 38 site photos at its inspections.
Is Glitz Residence 2 delayed?
The register lists construction as complete.
Who is building Glitz Residence 2?
The registered developer is Danube Properties Development. It has 23 other projects under construction in Dubai.
Which bank holds the escrow account for Glitz Residence 2?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.