The Fifth Tower construction progress
The Fifth Tower in Jumeirah Village Circle was registered to complete in July 2026 and is still under construction. At the last site inspection, in November 2026, it was 55% built. The developer is Object One Real Estate Development.
55%
Built, at the site inspection of 16 November 2026
4 months past its registered completion date
- Registered completion date
- July 2026
- Finish at recent pace
- July 2029
- Construction started
- March 2024
- First registered
- July 2024
- Developer
- Object One Real Estate Development
- Community
- Jumeirah Village Circle
- Units
- 345
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- البرج الخامس
- Project number
- 3048
- Site inspections
- 7
Schedule
The Fifth Tower was registered to complete in July 2026, 4 months ago, and is still under construction. Over the last year of inspections it has added about 1.4 points a month. Kept at that rate, the site would reach 100% around July 2029.
Site inspections
16 November 2026
55%+4.7 pts
4 August 2026
50%+5.0 pts
17 April 2026
45%+7.7 pts
6 November 2025
38%+12 pts
3 June 2025
26%+11 pts
21 January 2025
15%+15 pts
2 July 2024
0%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Object One Real Estate Development has 13 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in The Fifth Tower?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the The Fifth Tower handover date?
- The registered completion date was July 2026, and the register still lists The Fifth Tower as under construction. At the pace of its recent inspections the site would reach 100% around July 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on The Fifth Tower?
- The Fifth Tower was 55% built at the site inspection on 16 November 2026. The site has been inspected 7 times since July 2024. The Land Department took 57 site photos at its inspections.
- Is The Fifth Tower delayed?
- Yes. Its registered completion date of July 2026 has passed and the project is still listed as under construction.
- Who is building The Fifth Tower?
- The registered developer is Object One Real Estate Development. It has 12 other projects under construction in Dubai.
- Which bank holds the escrow account for The Fifth Tower?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- 1wood ResidenceAlso by Object One Real Estate Development. 94%.
- Ozone 1 ResidenceAlso by Object One Real Estate Development. 57%.
- Winner TowerAlso by Object One Real Estate Development. 36%.
- Vistara HouseAlso by Object One Real Estate Development. 10%, Due March 2027.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)