The Fifth Tower construction progress

The Fifth Tower in Jumeirah Village Circle is 50% built at the Land Department inspection of August 2026. Developer Object One Real Estate Development. Completion registered for July 2026.

50%

Built, at the Land Department site inspection of 4 August 2026

3 months past its registered completion date

Completion date (Land Department)
July 2026
Finish at recent pace
June 2029
Construction started
March 2024
Registered with the Land Department
July 2024
Units
345
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
البرج الخامس
Land Department project number
3048
Land Department site inspections
6

Schedule

The Fifth Tower was registered to complete in July 2026, 3 months ago, and is still under construction. Over the last year of inspections it has added about 1.4 points a month. Kept at that rate, the site would reach 100% around June 2029.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

4 August 2026

50%+5.0 pts

  • The Fifth Tower construction site, Land Department inspection photo 1, 4 August 2026
  • The Fifth Tower construction site, Land Department inspection photo 2, 4 August 2026
  • The Fifth Tower construction site, Land Department inspection photo 3, 4 August 2026
  • The Fifth Tower construction site, Land Department inspection photo 4, 4 August 2026

17 April 2026

45%+7.7 pts

  • The Fifth Tower construction site, Land Department inspection photo 1, 17 April 2026
  • The Fifth Tower construction site, Land Department inspection photo 2, 17 April 2026
  • The Fifth Tower construction site, Land Department inspection photo 3, 17 April 2026
  • The Fifth Tower construction site, Land Department inspection photo 4, 17 April 2026

6 November 2025

38%+12 pts

  • The Fifth Tower construction site, Land Department inspection photo 1, 6 November 2025
  • The Fifth Tower construction site, Land Department inspection photo 2, 6 November 2025
  • The Fifth Tower construction site, Land Department inspection photo 3, 6 November 2025
  • The Fifth Tower construction site, Land Department inspection photo 4, 6 November 2025

3 June 2025

26%+11 pts

  • The Fifth Tower construction site, Land Department inspection photo 1, 3 June 2025
  • The Fifth Tower construction site, Land Department inspection photo 2, 3 June 2025
  • The Fifth Tower construction site, Land Department inspection photo 3, 3 June 2025
  • The Fifth Tower construction site, Land Department inspection photo 4, 3 June 2025

21 January 2025

15%+15 pts

  • The Fifth Tower construction site, Land Department inspection photo 1, 21 January 2025
  • The Fifth Tower construction site, Land Department inspection photo 2, 21 January 2025
  • The Fifth Tower construction site, Land Department inspection photo 3, 21 January 2025
  • The Fifth Tower construction site, Land Department inspection photo 4, 21 January 2025

2 July 2024

0%

  • The Fifth Tower construction site, Land Department inspection photo 1, 2 July 2024
  • The Fifth Tower construction site, Land Department inspection photo 2, 2 July 2024

All 47 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average.

Object One Real Estate Development has 13 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in The Fifth Tower?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will The Fifth Tower be completed?
The completion date registered with the Dubai Land Department is July 2026. At the pace of its recent inspections the site would reach 100% around June 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of The Fifth Tower is built?
50%, measured at the Land Department site inspection on 4 August 2026. The Land Department engineers have inspected the site 6 times since July 2024.
Is The Fifth Tower delayed?
Yes. Its registered completion date of July 2026 has passed and the Land Department still lists it as under construction.
Who is building The Fifth Tower?
The registered developer is Object One Real Estate Development. It has 12 other projects under construction in Dubai.
Which bank holds the escrow account for The Fifth Tower?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.