The Fifth Tower construction progress

The Fifth Tower in Jumeirah Village Circle was registered to complete in July 2026 and is still under construction. At the last site inspection, in November 2026, it was 55% built. The developer is Object One Real Estate Development.

55%

Built, at the site inspection of 16 November 2026

4 months past its registered completion date

Registered completion date
July 2026
Finish at recent pace
July 2029
Construction started
March 2024
First registered
July 2024
Units
345
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
البرج الخامس
Project number
3048
Site inspections
7

Schedule

The Fifth Tower was registered to complete in July 2026, 4 months ago, and is still under construction. Over the last year of inspections it has added about 1.4 points a month. Kept at that rate, the site would reach 100% around July 2029.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

16 November 2026

55%+4.7 pts

  • The Fifth Tower construction site, inspection photo 1, 16 November 2026
  • The Fifth Tower construction site, inspection photo 2, 16 November 2026
  • The Fifth Tower construction site, inspection photo 3, 16 November 2026
  • The Fifth Tower construction site, inspection photo 4, 16 November 2026

4 August 2026

50%+5.0 pts

  • The Fifth Tower construction site, inspection photo 1, 4 August 2026
  • The Fifth Tower construction site, inspection photo 2, 4 August 2026
  • The Fifth Tower construction site, inspection photo 3, 4 August 2026
  • The Fifth Tower construction site, inspection photo 4, 4 August 2026

17 April 2026

45%+7.7 pts

  • The Fifth Tower construction site, inspection photo 1, 17 April 2026
  • The Fifth Tower construction site, inspection photo 2, 17 April 2026
  • The Fifth Tower construction site, inspection photo 3, 17 April 2026
  • The Fifth Tower construction site, inspection photo 4, 17 April 2026

6 November 2025

38%+12 pts

  • The Fifth Tower construction site, inspection photo 1, 6 November 2025
  • The Fifth Tower construction site, inspection photo 2, 6 November 2025
  • The Fifth Tower construction site, inspection photo 3, 6 November 2025
  • The Fifth Tower construction site, inspection photo 4, 6 November 2025

3 June 2025

26%+11 pts

  • The Fifth Tower construction site, inspection photo 1, 3 June 2025
  • The Fifth Tower construction site, inspection photo 2, 3 June 2025
  • The Fifth Tower construction site, inspection photo 3, 3 June 2025
  • The Fifth Tower construction site, inspection photo 4, 3 June 2025

21 January 2025

15%+15 pts

  • The Fifth Tower construction site, inspection photo 1, 21 January 2025
  • The Fifth Tower construction site, inspection photo 2, 21 January 2025
  • The Fifth Tower construction site, inspection photo 3, 21 January 2025
  • The Fifth Tower construction site, inspection photo 4, 21 January 2025

2 July 2024

0%

  • The Fifth Tower construction site, inspection photo 1, 2 July 2024
  • The Fifth Tower construction site, inspection photo 2, 2 July 2024

All 57 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Object One Real Estate Development has 13 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in The Fifth Tower?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Fifth Tower handover date?
The registered completion date was July 2026, and the register still lists The Fifth Tower as under construction. At the pace of its recent inspections the site would reach 100% around July 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The Fifth Tower?
The Fifth Tower was 55% built at the site inspection on 16 November 2026. The site has been inspected 7 times since July 2024. The Land Department took 57 site photos at its inspections.
Is The Fifth Tower delayed?
Yes. Its registered completion date of July 2026 has passed and the project is still listed as under construction.
Who is building The Fifth Tower?
The registered developer is Object One Real Estate Development. It has 12 other projects under construction in Dubai.
Which bank holds the escrow account for The Fifth Tower?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.