Winner Tower construction progress

Winner Tower in Jumeirah Village Triangle is 28% built at the Land Department inspection of July 2026. Developer Object One Real Estate Development.

28%

Built, at the Land Department site inspection of 31 July 2026

Finish at recent pace
November 2029
Construction started
March 2024
Registered with the Land Department
April 2024
Units
138
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
وينر تاور
Land Department project number
2991
Land Department site inspections
6

Schedule

Since April 2026 Winner Tower has added about 1.8 points a month. At that rate the site reaches 100% around November 2029. The Land Department has no completion date on record to compare it with.

0%25%50%75%100%20252026
Progress at each Land Department site inspection

Site inspections

31 July 2026

28%+5.8 pts

  • Winner Tower construction site, Land Department inspection photo 1, 31 July 2026
  • Winner Tower construction site, Land Department inspection photo 2, 31 July 2026
  • Winner Tower construction site, Land Department inspection photo 3, 31 July 2026
  • Winner Tower construction site, Land Department inspection photo 4, 31 July 2026

21 April 2026

22%+0.2 pts

  • Winner Tower construction site, Land Department inspection photo 1, 21 April 2026
  • Winner Tower construction site, Land Department inspection photo 2, 21 April 2026
  • Winner Tower construction site, Land Department inspection photo 3, 21 April 2026
  • Winner Tower construction site, Land Department inspection photo 4, 21 April 2026

20 April 2026

22%+7.3 pts

  • Winner Tower construction site, Land Department inspection photo 1, 20 April 2026
  • Winner Tower construction site, Land Department inspection photo 2, 20 April 2026
  • Winner Tower construction site, Land Department inspection photo 3, 20 April 2026
  • Winner Tower construction site, Land Department inspection photo 4, 20 April 2026

9 June 2025

14%+6.4 pts

  • Winner Tower construction site, Land Department inspection photo 1, 9 June 2025
  • Winner Tower construction site, Land Department inspection photo 2, 9 June 2025
  • Winner Tower construction site, Land Department inspection photo 3, 9 June 2025
  • Winner Tower construction site, Land Department inspection photo 4, 9 June 2025

17 February 2025

8.1%+8.1 pts

  • Winner Tower construction site, Land Department inspection photo 1, 17 February 2025
  • Winner Tower construction site, Land Department inspection photo 2, 17 February 2025
  • Winner Tower construction site, Land Department inspection photo 3, 17 February 2025
  • Winner Tower construction site, Land Department inspection photo 4, 17 February 2025

4 March 2024

0%

  • Winner Tower construction site, Land Department inspection photo 1, 4 March 2024
  • Winner Tower construction site, Land Department inspection photo 2, 4 March 2024
  • Winner Tower construction site, Land Department inspection photo 3, 4 March 2024

All 27 site photos, by inspection date

Context

Jumeirah Village Triangle has 31 projects under construction, 28% built on average.

Object One Real Estate Development has 13 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Winner Tower?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Winner Tower be completed?
The Land Department has no completion date on record for Winner Tower yet.
How much of Winner Tower is built?
28%, measured at the Land Department site inspection on 31 July 2026. The Land Department engineers have inspected the site 6 times since March 2024.
Who is building Winner Tower?
The registered developer is Object One Real Estate Development. It has 12 other projects under construction in Dubai.
Which bank holds the escrow account for Winner Tower?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.