The Pulse Boulevard Apartments-C1 construction progress

The register lists The Pulse Boulevard Apartments-C1 in Dubai South Residential District as complete, with a registered completion date of January 2021. Its last site inspection on record was in January 2021. The developer is Dubai South Properties Dwc.

100%

Built, at the site inspection of 11 January 2021

Construction complete

Registered completion date
January 2021
Construction started
April 2017
First registered
November 2016
Units
147
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
C1-ذا بلس بوليفارد
Project number
1828
Site inspections
6

Schedule

The register lists The Pulse Boulevard Apartments-C1 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2018201920202021
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

11 January 2021

100%+36 pts

  • The Pulse Boulevard Apartments-C1 construction site, inspection photo 1, 11 January 2021
  • The Pulse Boulevard Apartments-C1 construction site, inspection photo 2, 11 January 2021
  • The Pulse Boulevard Apartments-C1 construction site, inspection photo 3, 11 January 2021
  • The Pulse Boulevard Apartments-C1 construction site, inspection photo 4, 11 January 2021

26 January 2020

64%+17 pts

  • The Pulse Boulevard Apartments-C1 construction site, inspection photo 1, 26 January 2020
  • The Pulse Boulevard Apartments-C1 construction site, inspection photo 2, 26 January 2020
  • The Pulse Boulevard Apartments-C1 construction site, inspection photo 3, 26 January 2020
  • The Pulse Boulevard Apartments-C1 construction site, inspection photo 4, 26 January 2020

2 September 2019

47%+26 pts

  • The Pulse Boulevard Apartments-C1 construction site, inspection photo 1, 2 September 2019
  • The Pulse Boulevard Apartments-C1 construction site, inspection photo 2, 2 September 2019
  • The Pulse Boulevard Apartments-C1 construction site, inspection photo 3, 2 September 2019
  • The Pulse Boulevard Apartments-C1 construction site, inspection photo 4, 2 September 2019

8 April 2019

21%+17 pts

  • The Pulse Boulevard Apartments-C1 construction site, inspection photo 1, 8 April 2019
  • The Pulse Boulevard Apartments-C1 construction site, inspection photo 2, 8 April 2019
  • The Pulse Boulevard Apartments-C1 construction site, inspection photo 3, 8 April 2019
  • The Pulse Boulevard Apartments-C1 construction site, inspection photo 4, 8 April 2019

15 May 2018

3.7%+3.3 pts

  • The Pulse Boulevard Apartments-C1 construction site, inspection photo 1, 15 May 2018
  • The Pulse Boulevard Apartments-C1 construction site, inspection photo 2, 15 May 2018
  • The Pulse Boulevard Apartments-C1 construction site, inspection photo 3, 15 May 2018
  • The Pulse Boulevard Apartments-C1 construction site, inspection photo 4, 15 May 2018

27 December 2017

0.4%

  • The Pulse Boulevard Apartments-C1 construction site, inspection photo 1, 27 December 2017
  • The Pulse Boulevard Apartments-C1 construction site, inspection photo 2, 27 December 2017
  • The Pulse Boulevard Apartments-C1 construction site, inspection photo 3, 27 December 2017
  • The Pulse Boulevard Apartments-C1 construction site, inspection photo 4, 27 December 2017

All 57 site photos, by inspection date

Context

Dubai South Residential District has 37 projects under construction, 43% built on average.

Dubai South Properties Dwc has 19 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in The Pulse Boulevard Apartments-C1?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the The Pulse Boulevard Apartments-C1 handover date?
Construction of The Pulse Boulevard Apartments-C1 is recorded as complete, with a registered completion date of January 2021. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on The Pulse Boulevard Apartments-C1?
The Pulse Boulevard Apartments-C1 was 100% built at the site inspection on 11 January 2021. The site has been inspected 6 times since December 2017. The Land Department took 57 site photos at its inspections.
Is The Pulse Boulevard Apartments-C1 delayed?
The register lists construction as complete.
Who is building The Pulse Boulevard Apartments-C1?
The registered developer is Dubai South Properties Dwc. It has 19 other projects under construction in Dubai.
Which bank holds the escrow account for The Pulse Boulevard Apartments-C1?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.