Views Vii By Golden Woods construction progress
Views Vii By Golden Woods in Dubai South Residential District is 90% built at the Land Department inspection of May 2026. Developer Golden Wood Real Estate Development. Completion registered for July 2026.
90%
Built, at the Land Department site inspection of 8 May 2026
2 months past its registered completion date
- Completion date (Land Department)
- July 2026
- Finish at recent pace
- July 2026
- Construction started
- July 2024
- Registered with the Land Department
- October 2024
- Developer
- Golden Wood Real Estate Development
- Community
- Dubai South Residential District
- Units
- 68
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- لجولدن وودس Vii فيوز
- Land Department project number
- 3233
- Land Department site inspections
- 3
Schedule
Views Vii By Golden Woods was registered to complete in July 2026, 2 months ago, and is still under construction. Over the last year of inspections it has added about 5.1 points a month. Kept at that rate, the site would reach 100% around July 2026.
Site inspections
8 May 2026
90%+26 pts
3 December 2025
64%+64 pts
22 August 2024
0%
Context
Dubai South Residential District has 40 projects under construction, 40% built on average. Views Vii By Golden Woods is ahead of that average.
Golden Wood Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Views Vii By Golden Woods?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Views Vii By Golden Woods be completed?
- The completion date registered with the Dubai Land Department is July 2026. At the pace of its recent inspections the site would reach 100% around July 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Views Vii By Golden Woods is built?
- 90%, measured at the Land Department site inspection on 8 May 2026. The Land Department engineers have inspected the site 3 times since August 2024.
- Is Views Vii By Golden Woods delayed?
- Yes. Its registered completion date of July 2026 has passed and the Land Department still lists it as under construction.
- Who is building Views Vii By Golden Woods?
- The registered developer is Golden Wood Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Views Vii By Golden Woods?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Golden Wood Views 5Also by Golden Wood Real Estate Development. 89%.
- South LivingNearby in Dubai South Residential District. 89%.
- South Bay 1Nearby in Dubai South Residential District. 94%.
- South Bay 2Nearby in Dubai South Residential District. 94%.
- South Bay 3 PremiumNearby in Dubai South Residential District. 88%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.