Lincoln Star Residence construction progress
Lincoln Star Residence in Dubai South Residential District is 47% built at the Land Department inspection of February 2026. Developer Lincoln Star Real Estate Development. Completion registered for September 2026.
47%
Built, at the Land Department site inspection of 26 February 2026
0 months past its registered completion date
- Completion date (Land Department)
- September 2026
- Finish at recent pace
- August 2027
- Construction started
- October 2024
- Registered with the Land Department
- May 2025
- Developer
- Lincoln Star Real Estate Development
- Community
- Dubai South Residential District
- Units
- 48
- Escrow bank
- Emirates NBD
- Name in Arabic
- لينكولن ستار ريزيدنس
- Land Department project number
- 3102
- Land Department site inspections
- 4
Schedule
Lincoln Star Residence was registered to complete in September 2026, 1 month ago, and is still under construction. Over the last year of inspections it has added about 2.9 points a month. Kept at that rate, the site would reach 100% around August 2027.
Site inspections
26 February 2026
47%+17 pts
6 October 2025
31%+14 pts
21 April 2025
17%+17 pts
28 May 2024
0%
Context
Dubai South Residential District has 40 projects under construction, 40% built on average.
Own a unit in Lincoln Star Residence?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Lincoln Star Residence be completed?
- The completion date registered with the Dubai Land Department is September 2026. At the pace of its recent inspections the site would reach 100% around August 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Lincoln Star Residence is built?
- 47%, measured at the Land Department site inspection on 26 February 2026. The Land Department engineers have inspected the site 4 times since May 2024.
- Is Lincoln Star Residence delayed?
- Yes. Its registered completion date of September 2026 has passed and the Land Department still lists it as under construction.
- Who is building Lincoln Star Residence?
- The registered developer is Lincoln Star Real Estate Development.
- Which bank holds the escrow account for Lincoln Star Residence?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- South LivingNearby in Dubai South Residential District. 89%.
- South Bay 1Nearby in Dubai South Residential District. 94%.
- South Bay 2Nearby in Dubai South Residential District. 94%.
- South Bay 3 PremiumNearby in Dubai South Residential District. 88%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)