Lincoln Star Residence construction progress
Lincoln Star Residence in Dubai South Residential District was registered to complete in September 2026 and is still under construction. At the last site inspection, in October 2026, it was 55% built. The developer is Lincoln Star Real Estate Development.
55%
Built, at the site inspection of 27 October 2026
2 months past its registered completion date
- Registered completion date
- September 2026
- Finish at recent pace
- June 2030
- Construction started
- October 2024
- First registered
- May 2025
- Developer
- Lincoln Star Real Estate Development
- Community
- Dubai South Residential District
- Units
- 48
- Escrow bank
- Emirates NBD
- Name in Arabic
- لينكولن ستار ريزيدنس
- Project number
- 3102
- Site inspections
- 5
Schedule
Lincoln Star Residence was registered to complete in September 2026, 2 months ago, and is still under construction. Over the last year of inspections it has added about 1.0 points a month. Kept at that rate, the site would reach 100% around June 2030.
Site inspections
27 October 2026
55%+8.2 pts
26 February 2026
47%+17 pts
6 October 2025
31%+14 pts
21 April 2025
17%+17 pts
28 May 2024
0%
Context
Dubai South Residential District has 37 projects under construction, 43% built on average.
Own a unit in Lincoln Star Residence?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Lincoln Star Residence handover date?
- The registered completion date was September 2026, and the register still lists Lincoln Star Residence as under construction. At the pace of its recent inspections the site would reach 100% around June 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Lincoln Star Residence?
- Lincoln Star Residence was 55% built at the site inspection on 27 October 2026. The site has been inspected 5 times since May 2024. The Land Department took 36 site photos at its inspections.
- Is Lincoln Star Residence delayed?
- Yes. Its registered completion date of September 2026 has passed and the project is still listed as under construction.
- Who is building Lincoln Star Residence?
- The registered developer is Lincoln Star Real Estate Development.
- Which bank holds the escrow account for Lincoln Star Residence?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- South Bay 1Nearby in Dubai South Residential District. 94%, Due March 2025, passed.
- South Bay 2Nearby in Dubai South Residential District. 94%, Due May 2026, passed.
- South Bay 3 PremiumNearby in Dubai South Residential District. 88%.
- South Bay 4 PremiumNearby in Dubai South Residential District. 86%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)