The Eighty Three construction progress
The registered completion date for The Eighty Three in Dubai South Residential District is December 2026. At the last site inspection, in August 2026, it was 60% built. The developer is Oksa Developer.
60%
Built, at the site inspection of 11 August 2026
Running behind its date
- Registered completion date
- December 2026
- Finish at recent pace
- June 2027
- Construction started
- November 2024
- First registered
- November 2024
- Developer
- Oksa Developer
- Community
- Dubai South Residential District
- Units
- 70
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- الثالثه وثمانين
- Project number
- 3270
- Site inspections
- 6
Schedule
Between November 2025 and August 2026 the site added about 4.0 points a month. At that rate it would finish around June 2027, more than three months after its registered date of December 2026.
Site inspections
11 August 2026
60%+9.7 pts
30 April 2026
50%+12 pts
26 February 2026
38%+13 pts
17 November 2025
25%+14 pts
11 July 2025
11%+11 pts
4 September 2024
0%
Context
Dubai South Residential District has 37 projects under construction, 43% built on average.
Oksa Developer has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in The Eighty Three?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the The Eighty Three handover date?
- The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on The Eighty Three?
- The Eighty Three was 60% built at the site inspection on 11 August 2026. The site has been inspected 6 times since September 2024. The Land Department took 41 site photos at its inspections.
- Is The Eighty Three delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
- Who is building The Eighty Three?
- The registered developer is Oksa Developer. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for The Eighty Three?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- AristoAlso by Oksa Developer. 0.1%, Due December 2028.
- South Bay 1Nearby in Dubai South Residential District. 94%, Due March 2025, passed.
- South Bay 2Nearby in Dubai South Residential District. 94%, Due May 2026, passed.
- South Bay 3 PremiumNearby in Dubai South Residential District. 88%.
- South Bay 4 PremiumNearby in Dubai South Residential District. 86%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)