The Eighty Three construction progress

The Eighty Three in Dubai South Residential District is 60% built at the Land Department inspection of August 2026. Developer Oksa Developer. Completion registered for December 2026.

60%

Built, at the Land Department site inspection of 11 August 2026

Running behind its date

Completion date (Land Department)
December 2026
Finish at recent pace
June 2027
Construction started
November 2024
Registered with the Land Department
November 2024
Developer
Oksa Developer
Units
70
Escrow bank
First Abu Dhabi Bank
Name in Arabic
الثالثه وثمانين
Land Department project number
3270
Land Department site inspections
6

Schedule

Between November 2025 and August 2026 the site added about 4.0 points a month. At that rate it would finish around June 2027, more than three months after the December 2026 date registered with the Land Department.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

11 August 2026

60%+9.7 pts

  • The Eighty Three construction site, Land Department inspection photo 1, 11 August 2026
  • The Eighty Three construction site, Land Department inspection photo 2, 11 August 2026
  • The Eighty Three construction site, Land Department inspection photo 3, 11 August 2026
  • The Eighty Three construction site, Land Department inspection photo 4, 11 August 2026

30 April 2026

50%+12 pts

  • The Eighty Three construction site, Land Department inspection photo 1, 30 April 2026
  • The Eighty Three construction site, Land Department inspection photo 2, 30 April 2026
  • The Eighty Three construction site, Land Department inspection photo 3, 30 April 2026
  • The Eighty Three construction site, Land Department inspection photo 4, 30 April 2026

26 February 2026

38%+13 pts

  • The Eighty Three construction site, Land Department inspection photo 1, 26 February 2026
  • The Eighty Three construction site, Land Department inspection photo 2, 26 February 2026
  • The Eighty Three construction site, Land Department inspection photo 3, 26 February 2026
  • The Eighty Three construction site, Land Department inspection photo 4, 26 February 2026

17 November 2025

25%+14 pts

  • The Eighty Three construction site, Land Department inspection photo 1, 17 November 2025
  • The Eighty Three construction site, Land Department inspection photo 2, 17 November 2025
  • The Eighty Three construction site, Land Department inspection photo 3, 17 November 2025
  • The Eighty Three construction site, Land Department inspection photo 4, 17 November 2025

11 July 2025

11%+11 pts

  • The Eighty Three construction site, Land Department inspection photo 1, 11 July 2025
  • The Eighty Three construction site, Land Department inspection photo 2, 11 July 2025
  • The Eighty Three construction site, Land Department inspection photo 3, 11 July 2025
  • The Eighty Three construction site, Land Department inspection photo 4, 11 July 2025

4 September 2024

0%

  • The Eighty Three construction site, Land Department inspection photo 1, 4 September 2024
  • The Eighty Three construction site, Land Department inspection photo 2, 4 September 2024

All 41 site photos, by inspection date

Context

Dubai South Residential District has 40 projects under construction, 40% built on average.

Oksa Developer has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Eighty Three?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will The Eighty Three be completed?
The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around June 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of The Eighty Three is built?
60%, measured at the Land Department site inspection on 11 August 2026. The Land Department engineers have inspected the site 6 times since September 2024.
Is The Eighty Three delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building The Eighty Three?
The registered developer is Oksa Developer. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for The Eighty Three?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.