The Pulse Boulevard Apartments-C1 construction photos

57 photos from 6 site inspections, newest first. The percentage is how much of The Pulse Boulevard Apartments-C1 was built on the day of each visit.

11 January 2021100% built

26 January 202064% built

2 September 201947% built

8 April 201921% built

15 May 20183.7% built

27 December 20170.4% built

Back to The Pulse Boulevard Apartments-C1 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.