South Bay 3 Premium construction photos
34 photos taken by Dubai Land Department engineers at 5 site inspections, newest first. The percentage is how much of South Bay 3 Premium was built on the day of each visit.
23 July 202688% built
11 February 202663% built
23 July 202544% built
18 December 20249.0% built
14 August 20230% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.