South Bay 3 Premium construction photos

34 photos taken by Dubai Land Department engineers at 5 site inspections, newest first. The percentage is how much of South Bay 3 Premium was built on the day of each visit.

23 July 202688% built

11 February 202663% built

23 July 202544% built

18 December 20249.0% built

14 August 20230% built

Back to South Bay 3 Premium construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.