Harbour Lights construction progress

Harbour Lights in Dubai Maritime City is 64% built at the Land Department inspection of July 2026. Developer Damac J W F Investment. Completion registered for May 2027.

64%

Built, at the Land Department site inspection of 9 July 2026

On pace for its date

Completion date (Land Department)
May 2027
Finish at recent pace
April 2027
Construction started
February 2023
Registered with the Land Department
December 2022
Developer
Damac J W F Investment
Units
297
Escrow bank
Dubai Islamic Bank
Name in Arabic
هاربور لايتس
Land Department project number
2516
Land Department site inspections
9

Schedule

Since November 2025 Harbour Lights has added about 3.7 points a month. That puts 100% around April 2027, within three months of its registered completion date of May 2027.

0%25%50%75%100%20232024202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

9 July 2026

64%+11 pts

  • Harbour Lights construction site, Land Department inspection photo 1, 9 July 2026
  • Harbour Lights construction site, Land Department inspection photo 2, 9 July 2026
  • Harbour Lights construction site, Land Department inspection photo 3, 9 July 2026
  • Harbour Lights construction site, Land Department inspection photo 4, 9 July 2026

17 March 2026

53%+17 pts

  • Harbour Lights construction site, Land Department inspection photo 1, 17 March 2026
  • Harbour Lights construction site, Land Department inspection photo 2, 17 March 2026
  • Harbour Lights construction site, Land Department inspection photo 3, 17 March 2026
  • Harbour Lights construction site, Land Department inspection photo 4, 17 March 2026

19 November 2025

36%+10 pts

  • Harbour Lights construction site, Land Department inspection photo 1, 19 November 2025
  • Harbour Lights construction site, Land Department inspection photo 2, 19 November 2025
  • Harbour Lights construction site, Land Department inspection photo 3, 19 November 2025
  • Harbour Lights construction site, Land Department inspection photo 4, 19 November 2025

7 July 2025

26%+7.9 pts

  • Harbour Lights construction site, Land Department inspection photo 1, 7 July 2025
  • Harbour Lights construction site, Land Department inspection photo 2, 7 July 2025
  • Harbour Lights construction site, Land Department inspection photo 3, 7 July 2025
  • Harbour Lights construction site, Land Department inspection photo 4, 7 July 2025

21 January 2025

18%+9.3 pts

  • Harbour Lights construction site, Land Department inspection photo 1, 21 January 2025
  • Harbour Lights construction site, Land Department inspection photo 2, 21 January 2025
  • Harbour Lights construction site, Land Department inspection photo 3, 21 January 2025

5 July 2024

8.4%+4.2 pts

  • Harbour Lights construction site, Land Department inspection photo 1, 5 July 2024
  • Harbour Lights construction site, Land Department inspection photo 2, 5 July 2024

30 November 2023

4.2%+2.2 pts

  • Harbour Lights construction site, Land Department inspection photo 1, 30 November 2023
  • Harbour Lights construction site, Land Department inspection photo 2, 30 November 2023
  • Harbour Lights construction site, Land Department inspection photo 3, 30 November 2023
  • Harbour Lights construction site, Land Department inspection photo 4, 30 November 2023

20 July 2023

2.0%+2.0 pts

  • Harbour Lights construction site, Land Department inspection photo 1, 20 July 2023
  • Harbour Lights construction site, Land Department inspection photo 2, 20 July 2023
  • Harbour Lights construction site, Land Department inspection photo 3, 20 July 2023
  • Harbour Lights construction site, Land Department inspection photo 4, 20 July 2023

21 November 2022

0%

  • Harbour Lights construction site, Land Department inspection photo 1, 21 November 2022
  • Harbour Lights construction site, Land Department inspection photo 2, 21 November 2022

All 49 site photos, by inspection date

Context

Dubai Maritime City has 23 projects under construction, 29% built on average.

Own a unit in Harbour Lights?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Harbour Lights be completed?
The completion date registered with the Dubai Land Department is May 2027. At the pace of its recent inspections the site would reach 100% around April 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Harbour Lights is built?
64%, measured at the Land Department site inspection on 9 July 2026. The Land Department engineers have inspected the site 9 times since November 2022.
Is Harbour Lights delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of May 2027.
Who is building Harbour Lights?
The registered developer is Damac J W F Investment.
Which bank holds the escrow account for Harbour Lights?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.