Skip to content

Harbour Lights construction progress

The registered completion date for Harbour Lights in Dubai Maritime City is May 2027. At the last site inspection, in November 2026, it was 72% built. The developer is Damac J W F Investment.

72%

Built, at the site inspection of 20 November 2026

Running behind its date

Registered completion date
May 2027
Finish at recent pace
November 2027
Construction started
February 2023
First registered
December 2022
Developer
Damac J W F Investment
Units
297
Escrow bank
Dubai Islamic Bank
Name in Arabic
هاربور لايتس
Project number
2516
Site inspections
10

Schedule

Between March 2026 and November 2026 the site added about 2.4 points a month. At that rate it would finish around November 2027, more than three months after its registered date of May 2027.

0%25%50%75%100%20232024202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

20 November 2026

72%+8.1 pts

  • Harbour Lights construction site, inspection photo 1, 20 November 2026
  • Harbour Lights construction site, inspection photo 2, 20 November 2026
  • Harbour Lights construction site, inspection photo 3, 20 November 2026
  • Harbour Lights construction site, inspection photo 4, 20 November 2026

9 July 2026

64%+11 pts

  • Harbour Lights construction site, inspection photo 1, 9 July 2026
  • Harbour Lights construction site, inspection photo 2, 9 July 2026
  • Harbour Lights construction site, inspection photo 3, 9 July 2026
  • Harbour Lights construction site, inspection photo 4, 9 July 2026

17 March 2026

53%+17 pts

  • Harbour Lights construction site, inspection photo 1, 17 March 2026
  • Harbour Lights construction site, inspection photo 2, 17 March 2026
  • Harbour Lights construction site, inspection photo 3, 17 March 2026
  • Harbour Lights construction site, inspection photo 4, 17 March 2026

19 November 2025

36%+10 pts

  • Harbour Lights construction site, inspection photo 1, 19 November 2025
  • Harbour Lights construction site, inspection photo 2, 19 November 2025
  • Harbour Lights construction site, inspection photo 3, 19 November 2025
  • Harbour Lights construction site, inspection photo 4, 19 November 2025

7 July 2025

26%+7.9 pts

  • Harbour Lights construction site, inspection photo 1, 7 July 2025
  • Harbour Lights construction site, inspection photo 2, 7 July 2025
  • Harbour Lights construction site, inspection photo 3, 7 July 2025
  • Harbour Lights construction site, inspection photo 4, 7 July 2025

21 January 2025

18%+9.3 pts

  • Harbour Lights construction site, inspection photo 1, 21 January 2025
  • Harbour Lights construction site, inspection photo 2, 21 January 2025
  • Harbour Lights construction site, inspection photo 3, 21 January 2025

5 July 2024

8.4%+4.2 pts

  • Harbour Lights construction site, inspection photo 1, 5 July 2024
  • Harbour Lights construction site, inspection photo 2, 5 July 2024

30 November 2023

4.2%+2.2 pts

  • Harbour Lights construction site, inspection photo 1, 30 November 2023
  • Harbour Lights construction site, inspection photo 2, 30 November 2023
  • Harbour Lights construction site, inspection photo 3, 30 November 2023
  • Harbour Lights construction site, inspection photo 4, 30 November 2023

20 July 2023

2.0%+2.0 pts

  • Harbour Lights construction site, inspection photo 1, 20 July 2023
  • Harbour Lights construction site, inspection photo 2, 20 July 2023
  • Harbour Lights construction site, inspection photo 3, 20 July 2023
  • Harbour Lights construction site, inspection photo 4, 20 July 2023

21 November 2022

0%

  • Harbour Lights construction site, inspection photo 1, 21 November 2022
  • Harbour Lights construction site, inspection photo 2, 21 November 2022

All 59 site photos, by inspection date

Context

Dubai Maritime City has 23 projects under construction, 32% built on average.

Own a unit in Harbour Lights?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Harbour Lights handover date?
The registered completion date is May 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Harbour Lights?
Harbour Lights was 72% built at the site inspection on 20 November 2026. The site has been inspected 10 times since November 2022. The Land Department took 59 site photos at its inspections.
Is Harbour Lights delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2027.
Who is building Harbour Lights?
The registered developer is Damac J W F Investment.
Which bank holds the escrow account for Harbour Lights?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.