Weybridge Gardens 3 construction progress
Weybridge Gardens 3 in Dubai Land Residence Complex was registered to complete in August 2026 and is still under construction. At the last site inspection, in August 2026, it was 24% built. The developer is Leos Development.
24%
Built, at the site inspection of 5 August 2026
3 months past its registered completion date
- Registered completion date
- August 2026
- Finish at recent pace
- August 2029
- Construction started
- December 2024
- First registered
- September 2024
- Developer
- Leos Development
- Community
- Dubai Land Residence Complex
- Units
- 208
- Escrow bank
- Emirates Islamic Bank
- Name in Arabic
- ويبريدج غاردنز 3
- Project number
- 3164
- Site inspections
- 5
Schedule
Weybridge Gardens 3 was registered to complete in August 2026, 3 months ago, and is still under construction. Over the last year of inspections it has added about 2.1 points a month. Kept at that rate, the site would reach 100% around August 2029.
Site inspections
5 August 2026
24%+5.2 pts
1 June 2026
19%+3.2 pts
31 March 2026
15%+9.6 pts
18 November 2025
5.9%+5.9 pts
2 July 2024
0%
Context
Dubai Land Residence Complex has 63 projects under construction, 28% built on average.
Leos Development has 6 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Weybridge Gardens 3?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Weybridge Gardens 3 handover date?
- The registered completion date was August 2026, and the register still lists Weybridge Gardens 3 as under construction. At the pace of its recent inspections the site would reach 100% around August 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Weybridge Gardens 3?
- Weybridge Gardens 3 was 24% built at the site inspection on 5 August 2026. The site has been inspected 5 times since July 2024. The Land Department took 33 site photos at its inspections.
- Is Weybridge Gardens 3 delayed?
- Yes. Its registered completion date of August 2026 has passed and the project is still listed as under construction.
- Who is building Weybridge Gardens 3?
- The registered developer is Leos Development. It has 5 other projects under construction in Dubai.
- Which bank holds the escrow account for Weybridge Gardens 3?
- Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Cavendish SquareAlso by Leos Development. 4.6%.
- Weybridge Gardens 2Also by Leos Development. 34%.
- Kensington GardensAlso by Leos Development. 0%, Due September 2027.
- Weybridge Gardens 5Also by Leos Development. 0%, Due September 2027.
- Ag CentralNearby in Dubai Land Residence Complex. 59%, Due October 2026, passed.
- Ag SquareNearby in Dubai Land Residence Complex. 69%, Due September 2026, passed.
- Time 2Nearby in Dubai Land Residence Complex. 87%, Due June 2026, passed.
- Ag 7evenNearby in Dubai Land Residence Complex. 94%, Due March 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)