Weybridge Gardens 3 construction progress
Weybridge Gardens 3 in Dubai Land Residence Complex is 24% built at the Land Department inspection of August 2026. Developer Leos Development. Completion registered for August 2026.
24%
Built, at the Land Department site inspection of 5 August 2026
2 months past its registered completion date
- Completion date (Land Department)
- August 2026
- Finish at recent pace
- August 2029
- Construction started
- December 2024
- Registered with the Land Department
- September 2024
- Developer
- Leos Development
- Community
- Dubai Land Residence Complex
- Units
- 208
- Escrow bank
- Emirates Islamic Bank
- Name in Arabic
- ويبريدج غاردنز 3
- Land Department project number
- 3164
- Land Department site inspections
- 5
Schedule
Weybridge Gardens 3 was registered to complete in August 2026, 2 months ago, and is still under construction. Over the last year of inspections it has added about 2.1 points a month. Kept at that rate, the site would reach 100% around August 2029.
Site inspections
5 August 2026
24%+5.2 pts
1 June 2026
19%+3.2 pts
31 March 2026
15%+9.6 pts
18 November 2025
5.9%+5.9 pts
2 July 2024
0%
Context
Dubai Land Residence Complex has 65 projects under construction, 24% built on average.
Leos Development has 6 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Weybridge Gardens 3?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Weybridge Gardens 3 be completed?
- The completion date registered with the Dubai Land Department is August 2026. At the pace of its recent inspections the site would reach 100% around August 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Weybridge Gardens 3 is built?
- 24%, measured at the Land Department site inspection on 5 August 2026. The Land Department engineers have inspected the site 5 times since July 2024.
- Is Weybridge Gardens 3 delayed?
- Yes. Its registered completion date of August 2026 has passed and the Land Department still lists it as under construction.
- Who is building Weybridge Gardens 3?
- The registered developer is Leos Development. It has 5 other projects under construction in Dubai.
- Which bank holds the escrow account for Weybridge Gardens 3?
- Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Cavendish SquareAlso by Leos Development. 4.6%.
- Weybridge Gardens 2Also by Leos Development. 34%.
- Kensington GardensAlso by Leos Development. 0%, Due September 2027.
- Weybridge Gardens 5Also by Leos Development. 0%.
- Ag CentralNearby in Dubai Land Residence Complex. 59%, Due October 2026.
- Ag SquareNearby in Dubai Land Residence Complex. 69%.
- Time 2Nearby in Dubai Land Residence Complex. 87%, Due June 2026, passed.
- Ag 7evenNearby in Dubai Land Residence Complex. 94%, Due March 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)