Weybridge Gardens 2 construction progress

No completion date is registered for Weybridge Gardens 2 in Dubai Land Residence Complex yet. At the last site inspection, in August 2026, it was 34% built. The developer is Leos Development.

34%

Built, at the site inspection of 5 August 2026

Finish at recent pace
April 2029
Construction started
October 2024
First registered
May 2024
Units
288
Escrow bank
Emirates Islamic Bank
Name in Arabic
2 ويبريدج غاردنز
Project number
3007
Site inspections
7

Schedule

Since August 2025 Weybridge Gardens 2 has added about 2.0 points a month. At that rate the site reaches 100% around April 2029. No completion date is on record to compare it with.

0%25%50%75%100%20252026
Progress at each site inspection

Site inspections

5 August 2026

34%+5.9 pts

  • Weybridge Gardens 2 construction site, inspection photo 1, 5 August 2026
  • Weybridge Gardens 2 construction site, inspection photo 2, 5 August 2026
  • Weybridge Gardens 2 construction site, inspection photo 3, 5 August 2026
  • Weybridge Gardens 2 construction site, inspection photo 4, 5 August 2026

1 June 2026

28%+5.4 pts

  • Weybridge Gardens 2 construction site, inspection photo 1, 1 June 2026
  • Weybridge Gardens 2 construction site, inspection photo 2, 1 June 2026
  • Weybridge Gardens 2 construction site, inspection photo 3, 1 June 2026
  • Weybridge Gardens 2 construction site, inspection photo 4, 1 June 2026

31 March 2026

22%+5.1 pts

  • Weybridge Gardens 2 construction site, inspection photo 1, 31 March 2026
  • Weybridge Gardens 2 construction site, inspection photo 2, 31 March 2026
  • Weybridge Gardens 2 construction site, inspection photo 3, 31 March 2026
  • Weybridge Gardens 2 construction site, inspection photo 4, 31 March 2026

9 January 2026

17%+2.0 pts

  • Weybridge Gardens 2 construction site, inspection photo 1, 9 January 2026
  • Weybridge Gardens 2 construction site, inspection photo 2, 9 January 2026
  • Weybridge Gardens 2 construction site, inspection photo 3, 9 January 2026
  • Weybridge Gardens 2 construction site, inspection photo 4, 9 January 2026

18 November 2025

15%+5.1 pts

  • Weybridge Gardens 2 construction site, inspection photo 1, 18 November 2025
  • Weybridge Gardens 2 construction site, inspection photo 2, 18 November 2025
  • Weybridge Gardens 2 construction site, inspection photo 3, 18 November 2025
  • Weybridge Gardens 2 construction site, inspection photo 4, 18 November 2025

21 August 2025

10%+10 pts

  • Weybridge Gardens 2 construction site, inspection photo 1, 21 August 2025
  • Weybridge Gardens 2 construction site, inspection photo 2, 21 August 2025
  • Weybridge Gardens 2 construction site, inspection photo 3, 21 August 2025
  • Weybridge Gardens 2 construction site, inspection photo 4, 21 August 2025

20 March 2024

0%

  • Weybridge Gardens 2 construction site, inspection photo 1, 20 March 2024
  • Weybridge Gardens 2 construction site, inspection photo 2, 20 March 2024

All 64 site photos, by inspection date

Context

Dubai Land Residence Complex has 63 projects under construction, 28% built on average.

Leos Development has 6 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Weybridge Gardens 2?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Weybridge Gardens 2 handover date?
No completion date is on record for Weybridge Gardens 2 yet. Handover follows completion, so there is no date to give.
What is the latest construction update on Weybridge Gardens 2?
Weybridge Gardens 2 was 34% built at the site inspection on 5 August 2026. The site has been inspected 7 times since March 2024. The Land Department took 64 site photos at its inspections.
Who is building Weybridge Gardens 2?
The registered developer is Leos Development. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Weybridge Gardens 2?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.