Cavendish Square construction progress

No completion date is registered for Cavendish Square in Jumeirah Village Triangle yet. At the last site inspection, in August 2026, it was 4.6% built. The developer is Leos Development.

4.6%

Built, at the site inspection of 6 August 2026

Finish at recent pace
July 2144
Construction started
January 2024
First registered
January 2024
Units
141
Escrow bank
Emirates Islamic Bank
Name in Arabic
كافنديش سكوير
Project number
2866
Site inspections
5

Schedule

Since April 2026 Cavendish Square has added about 0.1 points a month. At that rate the site reaches 100% around July 2144. No completion date is on record to compare it with.

0%25%50%75%100%202420252026
Progress at each site inspection

Site inspections

6 August 2026

4.6%+0.3 pts

  • Cavendish Square construction site, inspection photo 1, 6 August 2026
  • Cavendish Square construction site, inspection photo 2, 6 August 2026
  • Cavendish Square construction site, inspection photo 3, 6 August 2026
  • Cavendish Square construction site, inspection photo 4, 6 August 2026

4 June 2026

4.4%

  • Cavendish Square construction site, inspection photo 1, 4 June 2026
  • Cavendish Square construction site, inspection photo 2, 4 June 2026
  • Cavendish Square construction site, inspection photo 3, 4 June 2026
  • Cavendish Square construction site, inspection photo 4, 4 June 2026

6 April 2026

4.4%+3.1 pts

  • Cavendish Square construction site, inspection photo 1, 6 April 2026
  • Cavendish Square construction site, inspection photo 2, 6 April 2026
  • Cavendish Square construction site, inspection photo 3, 6 April 2026

29 July 2025

1.2%+1.2 pts

  • Cavendish Square construction site, inspection photo 1, 29 July 2025
  • Cavendish Square construction site, inspection photo 2, 29 July 2025
  • Cavendish Square construction site, inspection photo 3, 29 July 2025
  • Cavendish Square construction site, inspection photo 4, 29 July 2025

28 November 2023

0%

  • Cavendish Square construction site, inspection photo 1, 28 November 2023
  • Cavendish Square construction site, inspection photo 2, 28 November 2023
  • Cavendish Square construction site, inspection photo 3, 28 November 2023

All 18 site photos, by inspection date

Context

Jumeirah Village Triangle has 29 projects under construction, 27% built on average.

Leos Development has 6 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Cavendish Square?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Cavendish Square handover date?
No completion date is on record for Cavendish Square yet. Handover follows completion, so there is no date to give.
What is the latest construction update on Cavendish Square?
Cavendish Square was 4.6% built at the site inspection on 6 August 2026. The site has been inspected 5 times since November 2023. The Land Department took 18 site photos at its inspections.
Who is building Cavendish Square?
The registered developer is Leos Development. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Cavendish Square?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.