Leos Development projects under construction
Leos Development has 6 projects under construction in Dubai, according to the Dubai Land Department. On average they are 10% built. 1 has passed its registered completion date. The next one due is Kensington Gardens, in September 2027.
- Weybridge Gardens 2Dubai Land Residence Complex34%No date set
- Weybridge Gardens 3Dubai Land Residence Complex24%Due August 2026, passed
- Cavendish SquareJumeirah Village Triangle4.6%No date set
- Weybridge Gardens 5Dubai Land Residence Complex0%No date set
- Hadley Heights 2Dubai Sports City0%Due October 2027
- Kensington GardensDubai Land Residence Complex0%Due September 2027
Reading these figures
Each percentage is the share of construction Land Department engineers recorded at their latest site visit. The completion date is the one the developer registered with the Land Department, and developers can apply to move it. Open a project to see its full inspection history, recent site photos and whether it is keeping pace with that date.