Time 1 construction progress

The register lists Time 1 in Dubai Land Residence Complex as complete, with a registered completion date of December 2022. Its last site inspection on record was in December 2023. The developer is Time Properties.

100%

Built, at the site inspection of 27 December 2023

Construction complete

Registered completion date
December 2022
Construction started
November 2017
First registered
October 2017
Units
286
Escrow bank
Dubai Islamic Bank
Name in Arabic
تايم 1
Project number
1973
Site inspections
11

Schedule

The register lists Time 1 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201820202022
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

27 December 2023

100%+8.7 pts

  • Time 1 construction site, inspection photo 1, 27 December 2023
  • Time 1 construction site, inspection photo 2, 27 December 2023
  • Time 1 construction site, inspection photo 3, 27 December 2023
  • Time 1 construction site, inspection photo 4, 27 December 2023

28 August 2023

91%+23 pts

  • Time 1 construction site, inspection photo 1, 28 August 2023
  • Time 1 construction site, inspection photo 2, 28 August 2023
  • Time 1 construction site, inspection photo 3, 28 August 2023
  • Time 1 construction site, inspection photo 4, 28 August 2023

25 April 2023

68%+11 pts

  • Time 1 construction site, inspection photo 1, 25 April 2023
  • Time 1 construction site, inspection photo 2, 25 April 2023
  • Time 1 construction site, inspection photo 3, 25 April 2023
  • Time 1 construction site, inspection photo 4, 25 April 2023

7 December 2022

57%+10 pts

  • Time 1 construction site, inspection photo 1, 7 December 2022
  • Time 1 construction site, inspection photo 2, 7 December 2022
  • Time 1 construction site, inspection photo 3, 7 December 2022
  • Time 1 construction site, inspection photo 4, 7 December 2022

4 August 2022

47%+14 pts

  • Time 1 construction site, inspection photo 1, 4 August 2022
  • Time 1 construction site, inspection photo 2, 4 August 2022
  • Time 1 construction site, inspection photo 3, 4 August 2022
  • Time 1 construction site, inspection photo 4, 4 August 2022

27 January 2022

33%+8.9 pts

  • Time 1 construction site, inspection photo 1, 27 January 2022
  • Time 1 construction site, inspection photo 2, 27 January 2022
  • Time 1 construction site, inspection photo 3, 27 January 2022
  • Time 1 construction site, inspection photo 4, 27 January 2022

23 August 2021

24%+6.4 pts

  • Time 1 construction site, inspection photo 1, 23 August 2021
  • Time 1 construction site, inspection photo 2, 23 August 2021
  • Time 1 construction site, inspection photo 3, 23 August 2021
  • Time 1 construction site, inspection photo 4, 23 August 2021

4 May 2021

18%+8.6 pts

  • Time 1 construction site, inspection photo 1, 4 May 2021
  • Time 1 construction site, inspection photo 2, 4 May 2021
  • Time 1 construction site, inspection photo 3, 4 May 2021
  • Time 1 construction site, inspection photo 4, 4 May 2021

20 October 2020

9.1%+5.6 pts

  • Time 1 construction site, inspection photo 1, 20 October 2020
  • Time 1 construction site, inspection photo 2, 20 October 2020
  • Time 1 construction site, inspection photo 3, 20 October 2020
  • Time 1 construction site, inspection photo 4, 20 October 2020

29 December 2019

3.5%+3.0 pts

  • Time 1 construction site, inspection photo 1, 29 December 2019
  • Time 1 construction site, inspection photo 2, 29 December 2019
  • Time 1 construction site, inspection photo 3, 29 December 2019
  • Time 1 construction site, inspection photo 4, 29 December 2019

All 91 site photos, by inspection date

Context

Dubai Land Residence Complex has 63 projects under construction, 28% built on average.

Time Properties has 2 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Time 1?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Time 1 handover date?
Construction of Time 1 is recorded as complete, with a registered completion date of December 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Time 1?
Time 1 was 100% built at the site inspection on 27 December 2023. The site has been inspected 11 times since April 2018. The Land Department took 91 site photos at its inspections.
Is Time 1 delayed?
The register lists construction as complete.
Who is building Time 1?
The registered developer is Time Properties. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Time 1?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.