91 photos from 11 site inspections, newest first. The percentage is how much of Time 1 was built on the day of each visit.

27 December 2023100% built

28 August 202391% built

25 April 202368% built

7 December 202257% built

4 August 202247% built

27 January 202233% built

23 August 202124% built

4 May 202118% built

20 October 20209.1% built

29 December 20193.5% built

15 April 20180.5% built

Back to Time 1 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.