Terra Tower construction progress
Terra Tower in Dubai Land Residence Complex is 7.4% built at the Land Department inspection of July 2026. Developer Dugasta Properties Development. Completion registered for April 2027.
7.4%
Built, at the Land Department site inspection of 8 July 2026
Running behind its date
- Completion date (Land Department)
- April 2027
- Finish at recent pace
- October 2039
- Construction started
- November 2024
- Registered with the Land Department
- October 2024
- Developer
- Dugasta Properties Development
- Community
- Dubai Land Residence Complex
- Units
- 366
- Escrow bank
- Mashreq Bank
- Name in Arabic
- برج تيرا
- Land Department project number
- 3278
- Land Department site inspections
- 4
Schedule
Between October 2025 and July 2026 the site added about 0.6 points a month. At that rate it would finish around October 2039, more than three months after the April 2027 date registered with the Land Department.
Site inspections
8 July 2026
7.4%+0.7 pts
2 March 2026
6.8%+4.1 pts
31 October 2025
2.7%+2.7 pts
12 September 2024
0%
Context
Dubai Land Residence Complex has 65 projects under construction, 24% built on average.
Dugasta Properties Development has 7 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Terra Tower?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Terra Tower be completed?
- The completion date registered with the Dubai Land Department is April 2027. At the pace of its recent inspections the site would reach 100% around October 2039. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Terra Tower is built?
- 7.4%, measured at the Land Department site inspection on 8 July 2026. The Land Department engineers have inspected the site 4 times since September 2024.
- Is Terra Tower delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of April 2027.
- Who is building Terra Tower?
- The registered developer is Dugasta Properties Development. It has 6 other projects under construction in Dubai.
- Which bank holds the escrow account for Terra Tower?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Moonsa ResidencesAlso by Dugasta Properties Development. 95%, Due August 2025, passed.
- Moonsa Residences 2Also by Dugasta Properties Development. 1.0%.
- Al Haseen Residence 3Also by Dugasta Properties Development. 10%, Due May 2027.
- Al Haseen Residence 4Also by Dugasta Properties Development. 12%, Due December 2026.
- Ag CentralNearby in Dubai Land Residence Complex. 59%, Due October 2026.
- Ag SquareNearby in Dubai Land Residence Complex. 69%.
- Time 2Nearby in Dubai Land Residence Complex. 87%, Due June 2026, passed.
- Ag 7evenNearby in Dubai Land Residence Complex. 94%, Due March 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.





.jpeg&w=3840&q=75)