Terra Tower construction progress

The registered completion date for Terra Tower in Dubai Land Residence Complex is April 2027. At the last site inspection, in July 2026, it was 7.4% built. The developer is Dugasta Properties Development.

7.4%

Built, at the site inspection of 8 July 2026

Running behind its date

Registered completion date
April 2027
Finish at recent pace
October 2039
Construction started
November 2024
First registered
October 2024
Units
366
Escrow bank
Mashreq Bank
Name in Arabic
برج تيرا
Project number
3278
Site inspections
4

Schedule

Between October 2025 and July 2026 the site added about 0.6 points a month. At that rate it would finish around October 2039, more than three months after its registered date of April 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

8 July 2026

7.4%+0.7 pts

  • Terra Tower construction site, inspection photo 1, 8 July 2026
  • Terra Tower construction site, inspection photo 2, 8 July 2026
  • Terra Tower construction site, inspection photo 3, 8 July 2026
  • Terra Tower construction site, inspection photo 4, 8 July 2026

2 March 2026

6.8%+4.1 pts

  • Terra Tower construction site, inspection photo 1, 2 March 2026
  • Terra Tower construction site, inspection photo 2, 2 March 2026
  • Terra Tower construction site, inspection photo 3, 2 March 2026
  • Terra Tower construction site, inspection photo 4, 2 March 2026

31 October 2025

2.7%+2.7 pts

  • Terra Tower construction site, inspection photo 1, 31 October 2025
  • Terra Tower construction site, inspection photo 2, 31 October 2025
  • Terra Tower construction site, inspection photo 3, 31 October 2025

12 September 2024

0%

  • Terra Tower construction site, inspection photo 1, 12 September 2024
  • Terra Tower construction site, inspection photo 2, 12 September 2024

All 14 site photos, by inspection date

Context

Dubai Land Residence Complex has 63 projects under construction, 28% built on average.

Dugasta Properties Development has 6 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Terra Tower?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Terra Tower handover date?
The registered completion date is April 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2039. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Terra Tower?
Terra Tower was 7.4% built at the site inspection on 8 July 2026. The site has been inspected 4 times since September 2024. The Land Department took 14 site photos at its inspections.
Is Terra Tower delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of April 2027.
Who is building Terra Tower?
The registered developer is Dugasta Properties Development. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Terra Tower?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.