Astra Residences construction progress
Astra Residences in Dubai South Residential District is 15% built at the Land Department inspection of July 2026. Developer Dugasta Properties Development. Completion registered for August 2027.
15%
Built, at the Land Department site inspection of 16 July 2026
Running behind its date
- Completion date (Land Department)
- August 2027
- Finish at recent pace
- January 2030
- Construction started
- January 2026
- Registered with the Land Department
- December 2025
- Developer
- Dugasta Properties Development
- Community
- Dubai South Residential District
- Units
- 108
- Escrow bank
- The National Bank of Fujairah
- Name in Arabic
- أسترا ريزيدنسز
- Land Department project number
- 4040
- Land Department site inspections
- 3
Schedule
Between November 2025 and July 2026 the site added about 2.0 points a month. At that rate it would finish around January 2030, more than three months after the August 2027 date registered with the Land Department.
Site inspections
16 July 2026
15%+5.0 pts
26 February 2026
10%+10 pts
26 November 2025
0%
Context
Dubai South Residential District has 40 projects under construction, 40% built on average.
Dugasta Properties Development has 7 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Astra Residences?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Astra Residences be completed?
- The completion date registered with the Dubai Land Department is August 2027. At the pace of its recent inspections the site would reach 100% around January 2030. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Astra Residences is built?
- 15%, measured at the Land Department site inspection on 16 July 2026. The Land Department engineers have inspected the site 3 times since November 2025.
- Is Astra Residences delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2027.
- Who is building Astra Residences?
- The registered developer is Dugasta Properties Development. It has 6 other projects under construction in Dubai.
- Which bank holds the escrow account for Astra Residences?
- The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Moonsa ResidencesAlso by Dugasta Properties Development. 95%, Due August 2025, passed.
- Terra TowerAlso by Dugasta Properties Development. 7.4%, Due April 2027.
- Moonsa Residences 2Also by Dugasta Properties Development. 1.0%.
- Al Haseen Residence 3Also by Dugasta Properties Development. 10%, Due May 2027.
- South LivingNearby in Dubai South Residential District. 89%.
- South Bay 1Nearby in Dubai South Residential District. 94%.
- South Bay 2Nearby in Dubai South Residential District. 94%.
- South Bay 3 PremiumNearby in Dubai South Residential District. 88%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.


.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)