Skip to content

Al Haseen Residence 3 construction progress

The registered completion date for Al Haseen Residence 3 in Saih Shuaib 2 is May 2027. At the last site inspection, in July 2026, it was 10% built. The developer is Dugasta Properties Development.

10%

Built, at the site inspection of 14 July 2026

Running behind its date

Registered completion date
May 2027
Finish at recent pace
January 2034
Construction started
April 2025
First registered
February 2025
Community
Saih Shuaib 2
Units
180
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
3 الحسين ريزيدينس
Project number
3484
Site inspections
4

Schedule

Between September 2025 and July 2026 the site added about 1.0 points a month. At that rate it would finish around January 2034, more than three months after its registered date of May 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

14 July 2026

10%+6.8 pts

  • Al Haseen Residence 3 construction site, inspection photo 1, 14 July 2026
  • Al Haseen Residence 3 construction site, inspection photo 2, 14 July 2026
  • Al Haseen Residence 3 construction site, inspection photo 3, 14 July 2026
  • Al Haseen Residence 3 construction site, inspection photo 4, 14 July 2026

25 February 2026

3.3%+2.7 pts

  • Al Haseen Residence 3 construction site, inspection photo 1, 25 February 2026
  • Al Haseen Residence 3 construction site, inspection photo 2, 25 February 2026
  • Al Haseen Residence 3 construction site, inspection photo 3, 25 February 2026

29 September 2025

0.6%+0.6 pts

  • Al Haseen Residence 3 construction site, inspection photo 1, 29 September 2025
  • Al Haseen Residence 3 construction site, inspection photo 2, 29 September 2025
  • Al Haseen Residence 3 construction site, inspection photo 3, 29 September 2025

27 January 2025

0%

  • Al Haseen Residence 3 construction site, inspection photo 1, 27 January 2025
  • Al Haseen Residence 3 construction site, inspection photo 2, 27 January 2025
  • Al Haseen Residence 3 construction site, inspection photo 3, 27 January 2025

All 14 site photos, by inspection date

Context

Saih Shuaib 2 has 6 projects under construction, 26% built on average.

Dugasta Properties Development has 6 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Al Haseen Residence 3?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Al Haseen Residence 3 handover date?
The registered completion date is May 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2034. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Al Haseen Residence 3?
Al Haseen Residence 3 was 10% built at the site inspection on 14 July 2026. The site has been inspected 4 times since January 2025. The Land Department took 14 site photos at its inspections.
Is Al Haseen Residence 3 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2027.
Who is building Al Haseen Residence 3?
The registered developer is Dugasta Properties Development. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Al Haseen Residence 3?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.