Seraph By Wadan construction progress

The registered completion date for Seraph By Wadan in Dubai Land Residence Complex is December 2027. At the last site inspection, in October 2026, it was 21% built. The developer is Wadan Real Estate Development.

21%

Built, at the site inspection of 27 October 2026

Running behind its date

Registered completion date
December 2027
Finish at recent pace
December 2028
Construction started
December 2025
First registered
October 2025
Units
190
Escrow bank
First Abu Dhabi Bank
Name in Arabic
سيراف من ودان
Project number
4109
Site inspections
4

Schedule

Between April 2026 and October 2026 the site added about 3.1 points a month. At that rate it would finish around December 2028, more than three months after its registered date of December 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

27 October 2026

21%+9.8 pts

  • Seraph By Wadan construction site, inspection photo 1, 27 October 2026
  • Seraph By Wadan construction site, inspection photo 2, 27 October 2026
  • Seraph By Wadan construction site, inspection photo 3, 27 October 2026
  • Seraph By Wadan construction site, inspection photo 4, 27 October 2026

22 July 2026

11%+9.4 pts

  • Seraph By Wadan construction site, inspection photo 1, 22 July 2026
  • Seraph By Wadan construction site, inspection photo 2, 22 July 2026
  • Seraph By Wadan construction site, inspection photo 3, 22 July 2026
  • Seraph By Wadan construction site, inspection photo 4, 22 July 2026

22 April 2026

1.7%+1.7 pts

  • Seraph By Wadan construction site, inspection photo 1, 22 April 2026
  • Seraph By Wadan construction site, inspection photo 2, 22 April 2026
  • Seraph By Wadan construction site, inspection photo 3, 22 April 2026
  • Seraph By Wadan construction site, inspection photo 4, 22 April 2026

24 September 2025

0%

  • Seraph By Wadan construction site, inspection photo 1, 24 September 2025
  • Seraph By Wadan construction site, inspection photo 2, 24 September 2025

All 19 site photos, by inspection date

Context

Dubai Land Residence Complex has 63 projects under construction, 28% built on average.

Wadan Real Estate Development has 5 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Seraph By Wadan?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Seraph By Wadan handover date?
The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Seraph By Wadan?
Seraph By Wadan was 21% built at the site inspection on 27 October 2026. The site has been inspected 4 times since September 2025. The Land Department took 19 site photos at its inspections.
Is Seraph By Wadan delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
Who is building Seraph By Wadan?
The registered developer is Wadan Real Estate Development. It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for Seraph By Wadan?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.