Seraph By Wadan construction progress

Seraph By Wadan in Dubai Land Residence Complex is 11% built at the Land Department inspection of July 2026. Developer Wadan Real Estate Development. Completion registered for December 2027.

11%

Built, at the Land Department site inspection of 22 July 2026

Running behind its date

Completion date (Land Department)
December 2027
Finish at recent pace
February 2033
Construction started
December 2025
Registered with the Land Department
October 2025
Units
190
Escrow bank
First Abu Dhabi Bank
Name in Arabic
سيراف من ودان
Land Department project number
4109
Land Department site inspections
3

Schedule

Between September 2025 and July 2026 the site added about 1.1 points a month. At that rate it would finish around February 2033, more than three months after the December 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

22 July 2026

11%+9.4 pts

  • Seraph By Wadan construction site, Land Department inspection photo 1, 22 July 2026
  • Seraph By Wadan construction site, Land Department inspection photo 2, 22 July 2026
  • Seraph By Wadan construction site, Land Department inspection photo 3, 22 July 2026
  • Seraph By Wadan construction site, Land Department inspection photo 4, 22 July 2026

22 April 2026

1.7%+1.7 pts

  • Seraph By Wadan construction site, Land Department inspection photo 1, 22 April 2026
  • Seraph By Wadan construction site, Land Department inspection photo 2, 22 April 2026
  • Seraph By Wadan construction site, Land Department inspection photo 3, 22 April 2026
  • Seraph By Wadan construction site, Land Department inspection photo 4, 22 April 2026

24 September 2025

0%

  • Seraph By Wadan construction site, Land Department inspection photo 1, 24 September 2025
  • Seraph By Wadan construction site, Land Department inspection photo 2, 24 September 2025

All 11 site photos, by inspection date

Context

Dubai Land Residence Complex has 65 projects under construction, 24% built on average.

Wadan Real Estate Development has 5 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Seraph By Wadan?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Seraph By Wadan be completed?
The completion date registered with the Dubai Land Department is December 2027. At the pace of its recent inspections the site would reach 100% around February 2033. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Seraph By Wadan is built?
11%, measured at the Land Department site inspection on 22 July 2026. The Land Department engineers have inspected the site 3 times since September 2025.
Is Seraph By Wadan delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
Who is building Seraph By Wadan?
The registered developer is Wadan Real Estate Development. It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for Seraph By Wadan?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.