Nuvana By Wadan construction progress

Nuvana By Wadan in Palm Deira is 25% built at the Land Department inspection of July 2026. Developer Wadan Real Estate Development. Completion registered for September 2027.

25%

Built, at the Land Department site inspection of 30 July 2026

On pace for its date

Completion date (Land Department)
September 2027
Finish at recent pace
October 2027
Construction started
September 2025
Registered with the Land Department
August 2025
Community
Palm Deira
Units
57
Escrow bank
First Abu Dhabi Bank
Name in Arabic
نوانا من ودان
Land Department project number
3885
Land Department site inspections
3

Schedule

Since April 2026 Nuvana By Wadan has added about 5.3 points a month. That puts 100% around October 2027, within three months of its registered completion date of September 2027.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

30 July 2026

25%+21 pts

  • Nuvana By Wadan construction site, Land Department inspection photo 1, 30 July 2026
  • Nuvana By Wadan construction site, Land Department inspection photo 2, 30 July 2026
  • Nuvana By Wadan construction site, Land Department inspection photo 3, 30 July 2026
  • Nuvana By Wadan construction site, Land Department inspection photo 4, 30 July 2026

1 April 2026

4.0%+4.0 pts

  • Nuvana By Wadan construction site, Land Department inspection photo 1, 1 April 2026
  • Nuvana By Wadan construction site, Land Department inspection photo 2, 1 April 2026
  • Nuvana By Wadan construction site, Land Department inspection photo 3, 1 April 2026
  • Nuvana By Wadan construction site, Land Department inspection photo 4, 1 April 2026

24 July 2025

0%

  • Nuvana By Wadan construction site, Land Department inspection photo 1, 24 July 2025
  • Nuvana By Wadan construction site, Land Department inspection photo 2, 24 July 2025

All 13 site photos, by inspection date

Context

Palm Deira has 95 projects under construction, 22% built on average.

Wadan Real Estate Development has 5 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Nuvana By Wadan?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Nuvana By Wadan be completed?
The completion date registered with the Dubai Land Department is September 2027. At the pace of its recent inspections the site would reach 100% around October 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Nuvana By Wadan is built?
25%, measured at the Land Department site inspection on 30 July 2026. The Land Department engineers have inspected the site 3 times since July 2025.
Is Nuvana By Wadan delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of September 2027.
Who is building Nuvana By Wadan?
The registered developer is Wadan Real Estate Development. It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for Nuvana By Wadan?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.