Cybele By Wadan construction progress
The registered completion date for Cybele By Wadan is December 2027. At the last site inspection, in July 2026, it was 2.0% built. The developer is Wadan Real Estate Development.
2.0%
Built, at the site inspection of 27 July 2026
Running behind its date
- Registered completion date
- December 2027
- Finish at recent pace
- May 2060
- Construction started
- December 2025
- First registered
- November 2025
- Developer
- Wadan Real Estate Development
- Units
- 232
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- سيبل من ودان
- Project number
- 4222
- Site inspections
- 3
Schedule
Between November 2025 and July 2026 the site added about 0.2 points a month. At that rate it would finish around May 2060, more than three months after its registered date of December 2027.
Site inspections
27 July 2026
2.0%+1.9 pts
22 April 2026
0.2%+0.2 pts
13 November 2025
0%
Context
Wadan Real Estate Development has 5 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Cybele By Wadan?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Cybele By Wadan handover date?
- The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2060. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Cybele By Wadan?
- Cybele By Wadan was 2.0% built at the site inspection on 27 July 2026. The site has been inspected 3 times since November 2025. The Land Department took 10 site photos at its inspections.
- Is Cybele By Wadan delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
- Who is building Cybele By Wadan?
- The registered developer is Wadan Real Estate Development. It has 4 other projects under construction in Dubai.
- Which bank holds the escrow account for Cybele By Wadan?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Nuvana By WadanAlso by Wadan Real Estate Development. 25%, Due September 2027.
- Seraph By WadanAlso by Wadan Real Estate Development. 21%, Due December 2027.
- Tresora By WadanAlso by Wadan Real Estate Development. 0%, Due March 2028.
- WestonAlso by Wadan Real Estate Development. 0%, Due December 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)