Safeer Residences 3 construction progress

The register lists Safeer Residences 3 in Dubai Land Residence Complex as complete, with a registered completion date of July 2018. Its last site inspection on record was in July 2018. The developer is Alseeb Real Estate Development.

100%

Built, at the site inspection of 1 July 2018

Construction complete

Registered completion date
July 2018
Construction started
May 2015
First registered
March 2016
Units
64
Escrow bank
Dubai Islamic Bank
Name in Arabic
سفير ريزدنس 3
Project number
1734
Site inspections
2

Schedule

The register lists Safeer Residences 3 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201620172018
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

1 July 2018

100%+1.0 pts

  • Safeer Residences 3 construction site, inspection photo 1, 1 July 2018
  • Safeer Residences 3 construction site, inspection photo 2, 1 July 2018
  • Safeer Residences 3 construction site, inspection photo 3, 1 July 2018
  • Safeer Residences 3 construction site, inspection photo 4, 1 July 2018

13 June 2018

99%

  • Safeer Residences 3 construction site, inspection photo 1, 13 June 2018
  • Safeer Residences 3 construction site, inspection photo 2, 13 June 2018
  • Safeer Residences 3 construction site, inspection photo 3, 13 June 2018
  • Safeer Residences 3 construction site, inspection photo 4, 13 June 2018

All 25 site photos, by inspection date

Context

Dubai Land Residence Complex has 63 projects under construction, 28% built on average.

Alseeb Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Safeer Residences 3?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Safeer Residences 3 handover date?
Construction of Safeer Residences 3 is recorded as complete, with a registered completion date of July 2018. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Safeer Residences 3?
Safeer Residences 3 was 100% built at the site inspection on 1 July 2018. The site has been inspected 2 times since June 2018. The Land Department took 25 site photos at its inspections.
Is Safeer Residences 3 delayed?
The register lists construction as complete.
Who is building Safeer Residences 3?
The registered developer is Alseeb Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Safeer Residences 3?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.