A 99 construction photos
36 photos taken by Dubai Land Department engineers at 6 site inspections, newest first. The percentage is how much of A 99 was built on the day of each visit.
1 July 202645% built
8 April 202642% built
10 October 202540% built
12 June 202535% built
20 December 202421% built
1 May 20240.3% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.