Verdana Residence construction photos
54 photos taken by Dubai Land Department engineers at 9 site inspections, newest first. The percentage is how much of Verdana Residence was built on the day of each visit.
3 June 202696% built
6 February 202694% built
20 October 202568% built
17 March 202543% built
18 September 202419% built
26 March 20246.5% built
6 December 20232.0% built
26 July 20230.1% built
27 October 20220% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.