Off-plan projects in Dubai Investment Park First
9 projects in Dubai Investment Park First are under construction according to the Dubai Land Department. On average they are 44% built. 3 have passed their registered completion date. The next one due is Olivia Residences, in December 2026.
- Verdana ResidenceReportage Prime Properties96%Due December 2025, passed
- Verdana (Phase 1)Reportage Prime Properties95%Due December 2025, passed
- Verdana(Phase 2)Reportage Prime Properties94%No date set
- Verdana 2Reportage Prime Properties56%No date set
- Olivia ResidencesKarma Real Estate Development38%Due December 2026
- Verdana Residence 2Reportage Prime Properties20%Due April 2026, passed
- Verdana 3Reportage Plus A Real Estate Development0.1%Due September 2028
- Verdana Residence 3Reportage Plus A Real Estate Development0%Due September 2028
- Verdana Residence 4Reportage Plus A Real Estate Development0%Due September 2028
Reading these figures
Each percentage is the share of construction Land Department engineers recorded at their latest site visit. The completion date is the one the developer registered with the Land Department, and developers can apply to move it. Open a project to see its latest inspections, the site photos and whether it is keeping pace with that date.
What happens at handover and how to snag a new home cover the steps after 100%.
Source: the Dubai Land Department’s Mashrooi register, read daily. Projects listed as cancelled or finished are not shown.