Olivia Residences construction progress

The registered completion date for Olivia Residences in Dubai Investment Park First is December 2026. At the last site inspection, in September 2026, it was 38% built. The developer is Karma Real Estate Development.

38%

Built, at the site inspection of 21 September 2026

Running behind its date

Registered completion date
December 2026
Finish at recent pace
February 2029
Construction started
October 2023
First registered
October 2023
Developer
Karma Real Estate Development
Units
231
Escrow bank
First Abu Dhabi Bank
Name in Arabic
اوليفيا ريزيدنسز
Project number
2752
Site inspections
8

Schedule

Between February 2026 and September 2026 the site added about 2.1 points a month. At that rate it would finish around February 2029, more than three months after its registered date of December 2026.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

21 September 2026

38%+7.4 pts

  • Olivia Residences construction site, inspection photo 1, 21 September 2026
  • Olivia Residences construction site, inspection photo 2, 21 September 2026
  • Olivia Residences construction site, inspection photo 3, 21 September 2026
  • Olivia Residences construction site, inspection photo 4, 21 September 2026

13 May 2026

31%+8.6 pts

  • Olivia Residences construction site, inspection photo 1, 13 May 2026
  • Olivia Residences construction site, inspection photo 2, 13 May 2026
  • Olivia Residences construction site, inspection photo 3, 13 May 2026
  • Olivia Residences construction site, inspection photo 4, 13 May 2026

5 February 2026

22%+9.9 pts

  • Olivia Residences construction site, inspection photo 1, 5 February 2026
  • Olivia Residences construction site, inspection photo 2, 5 February 2026
  • Olivia Residences construction site, inspection photo 3, 5 February 2026
  • Olivia Residences construction site, inspection photo 4, 5 February 2026

3 September 2025

12%+9.0 pts

  • Olivia Residences construction site, inspection photo 1, 3 September 2025
  • Olivia Residences construction site, inspection photo 2, 3 September 2025
  • Olivia Residences construction site, inspection photo 3, 3 September 2025

4 April 2025

3.3%+0.5 pts

  • Olivia Residences construction site, inspection photo 1, 4 April 2025
  • Olivia Residences construction site, inspection photo 2, 4 April 2025
  • Olivia Residences construction site, inspection photo 3, 4 April 2025
  • Olivia Residences construction site, inspection photo 4, 4 April 2025

17 December 2024

2.8%+0.1 pts

  • Olivia Residences construction site, inspection photo 1, 17 December 2024
  • Olivia Residences construction site, inspection photo 2, 17 December 2024
  • Olivia Residences construction site, inspection photo 3, 17 December 2024

11 September 2024

2.7%+2.7 pts

  • Olivia Residences construction site, inspection photo 1, 11 September 2024
  • Olivia Residences construction site, inspection photo 2, 11 September 2024
  • Olivia Residences construction site, inspection photo 3, 11 September 2024

29 August 2023

0%

  • Olivia Residences construction site, inspection photo 1, 29 August 2023
  • Olivia Residences construction site, inspection photo 2, 29 August 2023
  • Olivia Residences construction site, inspection photo 3, 29 August 2023

All 38 site photos, by inspection date

Context

Dubai Investment Park First has 9 projects under construction, 44% built on average.

Own a unit in Olivia Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Olivia Residences handover date?
The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Olivia Residences?
Olivia Residences was 38% built at the site inspection on 21 September 2026. The site has been inspected 8 times since August 2023. The Land Department took 38 site photos at its inspections.
Is Olivia Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building Olivia Residences?
The registered developer is Karma Real Estate Development.
Which bank holds the escrow account for Olivia Residences?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.