Verdana (Phase 1) construction photos

85 photos taken by Dubai Land Department engineers at 12 site inspections, newest first. The percentage is how much of Verdana (Phase 1) was built on the day of each visit.

3 June 202695% built

6 February 202693% built

6 November 202588% built

17 March 202569% built

23 December 202462% built

4 June 202440% built

26 March 202428% built

6 December 202323% built

25 September 202316% built

26 July 202312% built

2 March 20230.7% built

9 November 20220.1% built

Back to Verdana (Phase 1) construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.