Verdana 2 construction photos
48 photos taken by Dubai Land Department engineers at 8 site inspections, newest first. The percentage is how much of Verdana 2 was built on the day of each visit.
3 June 202656% built
11 February 202650% built
20 October 202539% built
17 March 202523% built
6 November 202411% built
26 March 20241.1% built
6 December 20230.3% built
25 September 20230% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.