Parkland construction photos

34 photos taken by Dubai Land Department engineers at 6 site inspections, newest first. The percentage is how much of Parkland was built on the day of each visit.

22 June 202650% built

12 February 202631% built

3 September 202517% built

21 May 202510.0% built

16 December 20245.2% built

12 June 20240% built

Back to Parkland construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.