City View Dubai Hills Residences construction progress

The registered completion date for City View Dubai Hills Residences in Dubai Hills Estate is March 2027. At the last site inspection, in August 2026, it was 39% built. The developer is City View Real Estate Development.

39%

Built, at the site inspection of 4 August 2026

Running behind its date

Registered completion date
March 2027
Finish at recent pace
May 2028
Construction started
September 2024
First registered
September 2024
Developer
City View Real Estate Development
Units
239
Escrow bank
United Bank Limited
Name in Arabic
سيتي فيو دبي هيلز ريزيدنسز
Project number
3148
Site inspections
6

Schedule

Between October 2025 and August 2026 the site added about 2.8 points a month. At that rate it would finish around May 2028, more than three months after its registered date of March 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

4 August 2026

39%+15 pts

  • City View Dubai Hills Residences construction site, inspection photo 1, 4 August 2026
  • City View Dubai Hills Residences construction site, inspection photo 2, 4 August 2026
  • City View Dubai Hills Residences construction site, inspection photo 3, 4 August 2026
  • City View Dubai Hills Residences construction site, inspection photo 4, 4 August 2026

17 March 2026

24%+11 pts

  • City View Dubai Hills Residences construction site, inspection photo 1, 17 March 2026
  • City View Dubai Hills Residences construction site, inspection photo 2, 17 March 2026
  • City View Dubai Hills Residences construction site, inspection photo 3, 17 March 2026
  • City View Dubai Hills Residences construction site, inspection photo 4, 17 March 2026

29 October 2025

13%+4.1 pts

  • City View Dubai Hills Residences construction site, inspection photo 1, 29 October 2025
  • City View Dubai Hills Residences construction site, inspection photo 2, 29 October 2025
  • City View Dubai Hills Residences construction site, inspection photo 3, 29 October 2025
  • City View Dubai Hills Residences construction site, inspection photo 4, 29 October 2025

9 July 2025

8.6%+1.0 pts

  • City View Dubai Hills Residences construction site, inspection photo 1, 9 July 2025
  • City View Dubai Hills Residences construction site, inspection photo 2, 9 July 2025
  • City View Dubai Hills Residences construction site, inspection photo 3, 9 July 2025
  • City View Dubai Hills Residences construction site, inspection photo 4, 9 July 2025

28 March 2025

7.6%+7.6 pts

  • City View Dubai Hills Residences construction site, inspection photo 1, 28 March 2025
  • City View Dubai Hills Residences construction site, inspection photo 2, 28 March 2025
  • City View Dubai Hills Residences construction site, inspection photo 3, 28 March 2025
  • City View Dubai Hills Residences construction site, inspection photo 4, 28 March 2025

12 August 2024

0%

  • City View Dubai Hills Residences construction site, inspection photo 1, 12 August 2024
  • City View Dubai Hills Residences construction site, inspection photo 2, 12 August 2024
  • City View Dubai Hills Residences construction site, inspection photo 3, 12 August 2024

All 31 site photos, by inspection date

Context

Dubai Hills Estate has 19 projects under construction, 44% built on average.

Own a unit in City View Dubai Hills Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the City View Dubai Hills Residences handover date?
The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on City View Dubai Hills Residences?
City View Dubai Hills Residences was 39% built at the site inspection on 4 August 2026. The site has been inspected 6 times since August 2024. The Land Department took 31 site photos at its inspections.
Is City View Dubai Hills Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building City View Dubai Hills Residences?
The registered developer is City View Real Estate Development.
Which bank holds the escrow account for City View Dubai Hills Residences?
United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.