City View Dubai Hills Residences construction progress
The registered completion date for City View Dubai Hills Residences in Dubai Hills Estate is March 2027. At the last site inspection, in August 2026, it was 39% built. The developer is City View Real Estate Development.
39%
Built, at the site inspection of 4 August 2026
Running behind its date
- Registered completion date
- March 2027
- Finish at recent pace
- May 2028
- Construction started
- September 2024
- First registered
- September 2024
- Developer
- City View Real Estate Development
- Community
- Dubai Hills Estate
- Units
- 239
- Escrow bank
- United Bank Limited
- Name in Arabic
- سيتي فيو دبي هيلز ريزيدنسز
- Project number
- 3148
- Site inspections
- 6
Schedule
Between October 2025 and August 2026 the site added about 2.8 points a month. At that rate it would finish around May 2028, more than three months after its registered date of March 2027.
Site inspections
4 August 2026
39%+15 pts
17 March 2026
24%+11 pts
29 October 2025
13%+4.1 pts
9 July 2025
8.6%+1.0 pts
28 March 2025
7.6%+7.6 pts
12 August 2024
0%
Context
Dubai Hills Estate has 19 projects under construction, 44% built on average.
Own a unit in City View Dubai Hills Residences?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the City View Dubai Hills Residences handover date?
- The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on City View Dubai Hills Residences?
- City View Dubai Hills Residences was 39% built at the site inspection on 4 August 2026. The site has been inspected 6 times since August 2024. The Land Department took 31 site photos at its inspections.
- Is City View Dubai Hills Residences delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
- Who is building City View Dubai Hills Residences?
- The registered developer is City View Real Estate Development.
- Which bank holds the escrow account for City View Dubai Hills Residences?
- United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Greenside ResidenceNearby in Dubai Hills Estate. 97%.
- Parkside HillsNearby in Dubai Hills Estate. 68%, Due June 2028.
- Park LaneNearby in Dubai Hills Estate. 55%, Due October 2028.
- Ellington House IVNearby in Dubai Hills Estate. 70%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)




.jpeg&w=3840&q=75)







.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)