Ellington House IV construction progress

No completion date is registered for Ellington House IV in Dubai Hills Estate yet. At the last site inspection, in July 2026, it was 70% built. The developer is Eh4 Development.

70%

Built, at the site inspection of 22 July 2026

Finish at recent pace
April 2027
Construction started
October 2023
First registered
January 2024
Developer
Eh4 Development
Units
110
Escrow bank
Emirates Islamic Bank
Name in Arabic
Iv إلينغتون هاوس
Project number
2790
Site inspections
8

Schedule

Since December 2025 Ellington House IV has added about 3.5 points a month. At that rate the site reaches 100% around April 2027. No completion date is on record to compare it with.

0%25%50%75%100%202420252026
Progress at each site inspection

Site inspections

22 July 2026

70%+20 pts

  • Ellington House IV construction site, inspection photo 1, 22 July 2026
  • Ellington House IV construction site, inspection photo 2, 22 July 2026
  • Ellington House IV construction site, inspection photo 3, 22 July 2026
  • Ellington House IV construction site, inspection photo 4, 22 July 2026

26 March 2026

50%+5.8 pts

  • Ellington House IV construction site, inspection photo 1, 26 March 2026
  • Ellington House IV construction site, inspection photo 2, 26 March 2026
  • Ellington House IV construction site, inspection photo 3, 26 March 2026
  • Ellington House IV construction site, inspection photo 4, 26 March 2026

10 December 2025

45%+6.3 pts

  • Ellington House IV construction site, inspection photo 1, 10 December 2025
  • Ellington House IV construction site, inspection photo 2, 10 December 2025
  • Ellington House IV construction site, inspection photo 3, 10 December 2025
  • Ellington House IV construction site, inspection photo 4, 10 December 2025

4 July 2025

38%+14 pts

  • Ellington House IV construction site, inspection photo 1, 4 July 2025
  • Ellington House IV construction site, inspection photo 2, 4 July 2025
  • Ellington House IV construction site, inspection photo 3, 4 July 2025
  • Ellington House IV construction site, inspection photo 4, 4 July 2025

29 January 2025

25%+14 pts

  • Ellington House IV construction site, inspection photo 1, 29 January 2025
  • Ellington House IV construction site, inspection photo 2, 29 January 2025
  • Ellington House IV construction site, inspection photo 3, 29 January 2025
  • Ellington House IV construction site, inspection photo 4, 29 January 2025

26 July 2024

11%+6.9 pts

  • Ellington House IV construction site, inspection photo 1, 26 July 2024
  • Ellington House IV construction site, inspection photo 2, 26 July 2024
  • Ellington House IV construction site, inspection photo 3, 26 July 2024
  • Ellington House IV construction site, inspection photo 4, 26 July 2024

4 April 2024

3.8%+3.8 pts

  • Ellington House IV construction site, inspection photo 1, 4 April 2024
  • Ellington House IV construction site, inspection photo 2, 4 April 2024
  • Ellington House IV construction site, inspection photo 3, 4 April 2024
  • Ellington House IV construction site, inspection photo 4, 4 April 2024

3 October 2023

0%

  • Ellington House IV construction site, inspection photo 1, 3 October 2023
  • Ellington House IV construction site, inspection photo 2, 3 October 2023

All 67 site photos, by inspection date

Context

Dubai Hills Estate has 19 projects under construction, 44% built on average.

Own a unit in Ellington House IV?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Ellington House IV handover date?
No completion date is on record for Ellington House IV yet. Handover follows completion, so there is no date to give.
What is the latest construction update on Ellington House IV?
Ellington House IV was 70% built at the site inspection on 22 July 2026. The site has been inspected 8 times since October 2023. The Land Department took 67 site photos at its inspections.
Who is building Ellington House IV?
The registered developer is Eh4 Development.
Which bank holds the escrow account for Ellington House IV?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.