Park Point construction progress

The register lists Park Point in Dubai Hills Estate as complete, with a registered completion date of April 2020. Its last site inspection on record was in February 2021. The developer is Dubai Hills Estate.

100%

Built, at the site inspection of 3 February 2021

Construction complete

Registered completion date
April 2020
Construction started
November 2016
First registered
September 2016
Units
338
Escrow bank
Emirates NBD
Name in Arabic
بارك بوينت
Project number
1812
Site inspections
14

Schedule

The register lists Park Point as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20172018201920202021
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

3 February 2021

100%+1.2 pts

  • Park Point construction site, inspection photo 1, 3 February 2021
  • Park Point construction site, inspection photo 2, 3 February 2021
  • Park Point construction site, inspection photo 3, 3 February 2021
  • Park Point construction site, inspection photo 4, 3 February 2021

22 December 2020

99%+8.7 pts

  • Park Point construction site, inspection photo 1, 22 December 2020
  • Park Point construction site, inspection photo 2, 22 December 2020
  • Park Point construction site, inspection photo 3, 22 December 2020
  • Park Point construction site, inspection photo 4, 22 December 2020

31 August 2020

90%+7.3 pts

  • Park Point construction site, inspection photo 1, 31 August 2020
  • Park Point construction site, inspection photo 2, 31 August 2020
  • Park Point construction site, inspection photo 3, 31 August 2020
  • Park Point construction site, inspection photo 4, 31 August 2020

18 May 2020

83%+6.1 pts

  • Park Point construction site, inspection photo 1, 18 May 2020
  • Park Point construction site, inspection photo 2, 18 May 2020
  • Park Point construction site, inspection photo 3, 18 May 2020
  • Park Point construction site, inspection photo 4, 18 May 2020

27 January 2020

77%+16 pts

  • Park Point construction site, inspection photo 1, 27 January 2020
  • Park Point construction site, inspection photo 2, 27 January 2020
  • Park Point construction site, inspection photo 3, 27 January 2020
  • Park Point construction site, inspection photo 4, 27 January 2020

27 August 2019

61%+7.6 pts

  • Park Point construction site, inspection photo 1, 27 August 2019
  • Park Point construction site, inspection photo 2, 27 August 2019
  • Park Point construction site, inspection photo 3, 27 August 2019
  • Park Point construction site, inspection photo 4, 27 August 2019

23 May 2019

54%+3.4 pts

  • Park Point construction site, inspection photo 1, 23 May 2019
  • Park Point construction site, inspection photo 2, 23 May 2019
  • Park Point construction site, inspection photo 3, 23 May 2019
  • Park Point construction site, inspection photo 4, 23 May 2019

7 February 2019

50%

  • Park Point construction site, inspection photo 1, 7 February 2019
  • Park Point construction site, inspection photo 2, 7 February 2019
  • Park Point construction site, inspection photo 3, 7 February 2019
  • Park Point construction site, inspection photo 4, 7 February 2019

2 October 2018

50%+5.4 pts

  • Park Point construction site, inspection photo 1, 2 October 2018
  • Park Point construction site, inspection photo 2, 2 October 2018
  • Park Point construction site, inspection photo 3, 2 October 2018
  • Park Point construction site, inspection photo 4, 2 October 2018

11 June 2018

45%+2.6 pts

  • Park Point construction site, inspection photo 1, 11 June 2018
  • Park Point construction site, inspection photo 2, 11 June 2018
  • Park Point construction site, inspection photo 3, 11 June 2018
  • Park Point construction site, inspection photo 4, 11 June 2018

All 145 site photos, by inspection date

Context

Dubai Hills Estate has 19 projects under construction, 44% built on average.

Dubai Hills Estate has 18 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Park Point?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Park Point handover date?
Construction of Park Point is recorded as complete, with a registered completion date of April 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Park Point?
Park Point was 100% built at the site inspection on 3 February 2021. The site has been inspected 14 times since June 2017. The Land Department took 145 site photos at its inspections.
Is Park Point delayed?
The register lists construction as complete.
Who is building Park Point?
The registered developer is Dubai Hills Estate. It has 18 other projects under construction in Dubai.
Which bank holds the escrow account for Park Point?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.