Park Point construction photos

145 photos from 14 site inspections, newest first. The percentage is how much of Park Point was built on the day of each visit.

3 February 2021100% built

22 December 202099% built

31 August 202090% built

18 May 202083% built

27 January 202077% built

27 August 201961% built

23 May 201954% built

7 February 201950% built

2 October 201850% built

11 June 201845% built

3 May 201842% built

30 January 201837% built

5 October 201720% built

7 June 201715% built

Back to Park Point construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.