Maple 2 construction progress

The register lists Maple 2 in Dubai Hills Estate as complete, with a registered completion date of September 2019. Its last site inspection on record was in November 2019. The developer is Dubai Hills Estate.

100%

Built, at the site inspection of 25 November 2019

Construction complete

Registered completion date
September 2019
Construction started
December 2016
First registered
October 2015
Units
667
Escrow bank
Dubai Islamic Bank
Name in Arabic
مابل 2
Project number
1690
Site inspections
12

Schedule

The register lists Maple 2 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201720182019
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

25 November 2019

100%+1.9 pts

  • Maple 2 construction site, inspection photo 1, 25 November 2019
  • Maple 2 construction site, inspection photo 2, 25 November 2019
  • Maple 2 construction site, inspection photo 3, 25 November 2019
  • Maple 2 construction site, inspection photo 4, 25 November 2019

5 November 2019

98%+2.2 pts

  • Maple 2 construction site, inspection photo 1, 5 November 2019
  • Maple 2 construction site, inspection photo 2, 5 November 2019
  • Maple 2 construction site, inspection photo 3, 5 November 2019
  • Maple 2 construction site, inspection photo 4, 5 November 2019

10 September 2019

96%+5.7 pts

  • Maple 2 construction site, inspection photo 1, 10 September 2019
  • Maple 2 construction site, inspection photo 2, 10 September 2019
  • Maple 2 construction site, inspection photo 3, 10 September 2019
  • Maple 2 construction site, inspection photo 4, 10 September 2019

21 April 2019

90%+9.9 pts

  • Maple 2 construction site, inspection photo 1, 21 April 2019
  • Maple 2 construction site, inspection photo 2, 21 April 2019
  • Maple 2 construction site, inspection photo 3, 21 April 2019
  • Maple 2 construction site, inspection photo 4, 21 April 2019

8 January 2019

80%+7.3 pts

  • Maple 2 construction site, inspection photo 1, 8 January 2019
  • Maple 2 construction site, inspection photo 2, 8 January 2019
  • Maple 2 construction site, inspection photo 3, 8 January 2019
  • Maple 2 construction site, inspection photo 4, 8 January 2019

1 November 2018

73%+4.5 pts

  • Maple 2 construction site, inspection photo 1, 1 November 2018
  • Maple 2 construction site, inspection photo 2, 1 November 2018
  • Maple 2 construction site, inspection photo 3, 1 November 2018
  • Maple 2 construction site, inspection photo 4, 1 November 2018

11 September 2018

69%+8.4 pts

  • Maple 2 construction site, inspection photo 1, 11 September 2018
  • Maple 2 construction site, inspection photo 2, 11 September 2018
  • Maple 2 construction site, inspection photo 3, 11 September 2018
  • Maple 2 construction site, inspection photo 4, 11 September 2018

24 May 2018

60%+4.5 pts

  • Maple 2 construction site, inspection photo 1, 24 May 2018
  • Maple 2 construction site, inspection photo 2, 24 May 2018
  • Maple 2 construction site, inspection photo 3, 24 May 2018
  • Maple 2 construction site, inspection photo 4, 24 May 2018

16 April 2018

56%+24 pts

  • Maple 2 construction site, inspection photo 1, 16 April 2018
  • Maple 2 construction site, inspection photo 2, 16 April 2018
  • Maple 2 construction site, inspection photo 3, 16 April 2018
  • Maple 2 construction site, inspection photo 4, 16 April 2018

7 December 2017

32%+12 pts

  • Maple 2 construction site, inspection photo 1, 7 December 2017
  • Maple 2 construction site, inspection photo 2, 7 December 2017
  • Maple 2 construction site, inspection photo 3, 7 December 2017
  • Maple 2 construction site, inspection photo 4, 7 December 2017

All 115 site photos, by inspection date

Context

Dubai Hills Estate has 19 projects under construction, 44% built on average.

Dubai Hills Estate has 18 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Maple 2?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Maple 2 handover date?
Construction of Maple 2 is recorded as complete, with a registered completion date of September 2019. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Maple 2?
Maple 2 was 100% built at the site inspection on 25 November 2019. The site has been inspected 12 times since January 2017. The Land Department took 115 site photos at its inspections.
Is Maple 2 delayed?
The register lists construction as complete.
Who is building Maple 2?
The registered developer is Dubai Hills Estate. It has 18 other projects under construction in Dubai.
Which bank holds the escrow account for Maple 2?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.