Maple 2 construction photos

115 photos from 12 site inspections, newest first. The percentage is how much of Maple 2 was built on the day of each visit.

25 November 2019100% built

5 November 201998% built

10 September 201996% built

21 April 201990% built

8 January 201980% built

1 November 201873% built

11 September 201869% built

24 May 201860% built

16 April 201856% built

7 December 201732% built

3 August 201720% built

22 January 20175.9% built

Back to Maple 2 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.