Golf Grand construction progress

The register lists Golf Grand in Dubai Hills Estate as complete, with a registered completion date of March 2027. Its last site inspection on record was in January 2026. The developer is Dubai Hills Estate.

100%

Built, at the site inspection of 16 January 2026

Construction complete

Registered completion date
March 2027
Construction started
August 2023
First registered
March 2023
Units
329
Escrow bank
Emirates NBD
Name in Arabic
جولف جراند
Project number
2599
Site inspections
9

Schedule

The register lists Golf Grand as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2024202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

16 January 2026

100%+4.0 pts

  • Golf Grand construction site, inspection photo 1, 16 January 2026
  • Golf Grand construction site, inspection photo 2, 16 January 2026
  • Golf Grand construction site, inspection photo 3, 16 January 2026
  • Golf Grand construction site, inspection photo 4, 16 January 2026

20 October 2025

96%+19 pts

  • Golf Grand construction site, inspection photo 1, 20 October 2025
  • Golf Grand construction site, inspection photo 2, 20 October 2025
  • Golf Grand construction site, inspection photo 3, 20 October 2025
  • Golf Grand construction site, inspection photo 4, 20 October 2025

30 July 2025

77%+7.1 pts

  • Golf Grand construction site, inspection photo 1, 30 July 2025
  • Golf Grand construction site, inspection photo 2, 30 July 2025
  • Golf Grand construction site, inspection photo 3, 30 July 2025
  • Golf Grand construction site, inspection photo 4, 30 July 2025

12 June 2025

70%+15 pts

  • Golf Grand construction site, inspection photo 1, 12 June 2025
  • Golf Grand construction site, inspection photo 2, 12 June 2025
  • Golf Grand construction site, inspection photo 3, 12 June 2025
  • Golf Grand construction site, inspection photo 4, 12 June 2025

26 February 2025

55%+26 pts

  • Golf Grand construction site, inspection photo 1, 26 February 2025
  • Golf Grand construction site, inspection photo 2, 26 February 2025
  • Golf Grand construction site, inspection photo 3, 26 February 2025
  • Golf Grand construction site, inspection photo 4, 26 February 2025

21 August 2024

29%+20 pts

  • Golf Grand construction site, inspection photo 1, 21 August 2024
  • Golf Grand construction site, inspection photo 2, 21 August 2024
  • Golf Grand construction site, inspection photo 3, 21 August 2024
  • Golf Grand construction site, inspection photo 4, 21 August 2024

22 March 2024

8.5%+6.0 pts

  • Golf Grand construction site, inspection photo 1, 22 March 2024
  • Golf Grand construction site, inspection photo 2, 22 March 2024
  • Golf Grand construction site, inspection photo 3, 22 March 2024
  • Golf Grand construction site, inspection photo 4, 22 March 2024

25 September 2023

2.5%+2.5 pts

  • Golf Grand construction site, inspection photo 1, 25 September 2023
  • Golf Grand construction site, inspection photo 2, 25 September 2023
  • Golf Grand construction site, inspection photo 3, 25 September 2023
  • Golf Grand construction site, inspection photo 4, 25 September 2023

28 February 2023

0%

  • Golf Grand construction site, inspection photo 1, 28 February 2023
  • Golf Grand construction site, inspection photo 2, 28 February 2023
  • Golf Grand construction site, inspection photo 3, 28 February 2023

All 60 site photos, by inspection date

Context

Dubai Hills Estate has 19 projects under construction, 44% built on average.

Dubai Hills Estate has 18 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Golf Grand?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Golf Grand handover date?
Construction of Golf Grand is recorded as complete, with a registered completion date of March 2027. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Golf Grand?
Golf Grand was 100% built at the site inspection on 16 January 2026. The site has been inspected 9 times since February 2023. The Land Department took 60 site photos at its inspections.
Is Golf Grand delayed?
The register lists construction as complete.
Who is building Golf Grand?
The registered developer is Dubai Hills Estate. It has 18 other projects under construction in Dubai.
Which bank holds the escrow account for Golf Grand?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.