Golf Grand construction photos

60 photos from 9 site inspections, newest first. The percentage is how much of Golf Grand was built on the day of each visit.

16 January 2026100% built

20 October 202596% built

30 July 202577% built

12 June 202570% built

26 February 202555% built

21 August 202429% built

22 March 20248.5% built

25 September 20232.5% built

28 February 20230% built

Back to Golf Grand construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.